Substation · England, United Kingdom

Cricklade Primary

Cricklade Primary is a substation in England, United Kingdom, connected by Southern Electric Power Distribution plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEnglandSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorSouthern Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Demand headroom4.73 MVASSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Generation headroom0 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Transformers2 x 7.5 / 15MVASSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LevelPrimarySSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Fed fromCirencester BSPSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Fed fromMinety GSPSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Congestion (offtake)None (green on the heat map)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Congestion (feed-in)Full (red on the heat map, limited by upstream thermal capacity)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage33 kV (levels 33, 11 kV)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates51.6382, -1.8656SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Research on this substation and its grid operator.Who owns it up to the parent company, its headroom, congestion and the land around it, and an introduction to the grid operator.

Request research

Nearby

Within 50 km of this substation: 363 power plants (131 operating, 2,235 MW), 276 grid connections (97 operating, 1,188 MW), 11 data centers and 1 AI supercomputer, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Malmesbury Road Solar FarmPower plant13 MWPermitted0.7 km
Land at Windmill Farm - Solar grid connectionGrid connection13 MWPlanned0.9 km
Chelworth Industrial Estate Solar ParkPower plant1 MWOperating1.7 km
North Wiltshire Biomass Power PlantPower plant5.5 MWCancelled2.4 km
Down Ampney Airfield Quarry grid connectionGrid connection2.45 MWPlanned3.2 km
Bentham Solar Farm grid connectionGrid connection8.27 MWOperating3.7 km
Nationwide Swindon Technology CentreData center——7.6 km
VodafoneData center——9.7 km
nLighten SwindonData center——10 km

Grid operator and place

Grid connections attached to this substation

More from Southern Electric Power Distribution plc

Other substations in England

All 1666 substations in England, United Kingdom

Data on this page