Bushey Mill Grid 11kV Substation

Bushey Mill Grid 11kV Substation is an 11 kV primary substation in England, United Kingdom, with 39.9 MVA of demand headroom and 100 MVA of generation headroom, operated by Eastern Power Networks plc (UK Power Networks, East England licence area).

Map: where Bushey Mill Grid 11kV lies
51.6717, -0.3819 on OpenStreetMap

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEnglandUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Grid operatorEastern Power Networks plc (UK Power Networks, East England licence area)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Demand headroom39.9 MVAUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Generation headroom100 MVAUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Firm capacity78 MVAUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
LevelPrimary substationUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Voltage11 kVUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Coordinates51.6717, -0.3819UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026

Research on this substation and the land around it.Its headroom, connection queue and congestion, who owns the land around it, and an introduction to those owners.

Nearby

Within 50 km of this substation: 381 power plants (131 operating, 2,720 MW), 352 grid connections (242 operating, 2,234 MW), 152 data centers (1 operating, 88 MW), 1 transmission line and 1 AI supercomputer, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Mirror Colour Print Ltd grid connectionGrid connection7.2 MWOperating1.1 km
Elstree Substation, Hilfield Lane - Battery Energy StoragePower plant400 MWCancelled3.2 km
Hilfield Lane, Aldenham - Battery Energy StoragePower plant170 MWPermitted3.6 km
Hilfield - Solar arrays & Battery storagePower plant49.9 MWCancelled3.6 km
The Chess BuildingData center——4.5 km
Bio Products Laboratory grid connectionGrid connection2 MWOperating5.1 km
Handley Page B grid connectionGrid connection4 MWOperating5.6 km
NTT Hemel Hempstead 4Data center——10 km
NTT Hemel Hempstead 3Data center——11 km

Grid operator and place

More from Eastern Power Networks plc

Other substations in England

All 2633 substations in England, United Kingdom