RARE CONTEXT Request research

Substation · the United Kingdom

Abergele T1 / Pensarn T1 Substation

Abergele T1 / Pensarn T1 Substation is a 33 kV primary substation in the United Kingdom, with 0.65 MVA of demand headroom and 3.29 MVA of generation headroom, operated by SP Manweb plc (SP Energy Networks, North Wales, Merseyside and Cheshire licence area).

Map: where Abergele T1 / Pensarn T1 lies
53.2931, -3.5817 on OpenStreetMap

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceABERGELE T1 / PENSARN T1SP Energy Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
LocationUnited KingdomSP Energy Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Grid operatorSP Manweb plc (SP Energy Networks, North Wales, Merseyside and Cheshire licence area)SP Energy Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Demand headroom0.65 MVASP Energy Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Generation headroom3.29 MVASP Energy Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Firm capacity10 MVASP Energy Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
LevelPrimary substationSP Energy Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Voltage33 kV (levels 33, 11 kV)SP Energy Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Coordinates53.2931, -3.5817SP Energy Networks open data portal · CC BY 4.0 · checked 25 Oct 2026

Research on this substation and the land around it.Its headroom, connection queue and congestion, who owns the land around it, and an introduction to those owners.

Nearby

Within 50 km of this substation: 136 power plants (52 operating, 7,445 MW), 132 grid connections (106 operating, 1,288 MW), 2 data centers and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Rhyl Flats grid connectionGrid connection92 MWOperating2.3 km
Llandulas Landfill SchemePower plant2.9 MWOperating3.5 km
Kinmel Estate Solar Farm Ph 2 grid connectionGrid connection28 MWOperating3.8 km
Kinmel 1 CICPower plant5 MWOperating4.0 km
Neud Trydan grid connectionGrid connection1 MWOperating4.2 km
Bodelwyddan, Abergele Road - Solar Farm & Battery StoragePower plant110 MWPlanned5.4 km
North Wales Wind Farms ConnectionTransmission line—Permitted24 km
nLighten Edge Data Centre LiverpoolData center——41 km
nLighten ChesterData center——44 km

Grid operator and place

More from SP Manweb plc