Wood Farm Solar Park (linked site) is a cancelled power plant in Flintshire, Wales, United Kingdom, with 5 MW of capacity, operated by SEP Solar.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationFlintshire (coordinates), WalesDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressOpp. Kingston Lane, Manor Farm, Deeside Lane, Sealand, Chester, CH1 6BPDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusCancelled (appeal refused)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date11 May 2015 (reference 53687, planning authority Flintshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date14 Dec 2016 (appeal refused, reference 53687, planning authority Flintshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date4 Apr 2016 (refused, reference 53687, planning authority Flintshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorSEP SolarDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity5 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area10.3 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates53.2010, -2.9596DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit refused (appeal refused, planning authority Flintshire, reference 53687)
  2. Permit refused (planning authority Flintshire, reference 53687)
  3. Permit applied for (planning authority Flintshire, reference 53687)

How it compares

Wood Farm Solar Park (linked site) is the 231st-largest of 424 power plants in Wales and the 2,742nd-largest of 5,050 in the United Kingdom by capacity; its 5 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
Wales231st of 4249,068 MW<0.1%
United Kingdom2,742nd of 5,050115,622 MW<0.1%
All power plants in our data8,380th of 12,0321,190,447 MW<0.1%

Nearby

Within 50 km of this power plant: 74 grid connections (46 operating, 384 MW), 55 substations, 7 data centers, 3 gas storage facilities and 2 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
nLighten ChesterData center——5.3 km
nLighten Edge Data Centre LiverpoolData center——16 km
The Babbage CentreData center——20 km
Bold GSPSubstation——32 km
Keuper Underground Gas Storage Facility Material Change 1Gas storage facility—Planned34 km
Salinae Hydrogen Storage projectGas storage facility—Planned34 km
Keuper Gas Storage ProjectGas storage facility—Permitted35 km
Unit 1 Junction Lane grid connectionGrid connection5.26 MWPlanned35 km
Newton Le WillowsSubstation——36 km