Werfa is a cancelled power plant in Bridgend, Wales, United Kingdom, with 47.5 MW of capacity, operated by AMEC.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationBridgend (coordinates), WalesDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressNant Y Moel, Bridgend, Mid GlamorganDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusCancelled (appeal refused)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Onshore or offshoreOnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date28 Sept 2001 (reference P/01/887/FUL, planning authority Bridgend)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date13 Mar 2002 (refused, reference P/01/887/FUL, planning authority Bridgend)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date25 Aug 2004 (appeal refused, reference P/01/887/FUL, planning authority Bridgend)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorAMECDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity47.5 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Units19 units (2.5 MW per unit)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyWind OnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.6394, -3.5553DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit refused (appeal refused, planning authority Bridgend, reference P/01/887/FUL)
  2. Permit refused (planning authority Bridgend, reference P/01/887/FUL)
  3. Permit applied for (planning authority Bridgend, reference P/01/887/FUL)

How it compares

Werfa is the 32nd-largest of 424 power plants in Wales and the 513th-largest of 5,050 in the United Kingdom by capacity; its 47.5 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
Wales32nd of 4249,068 MW0.52%
United Kingdom513th of 5,050115,622 MW<0.1%
All power plants in our data2,051st of 12,0321,190,447 MW<0.1%

Nearby

Within 50 km of this power plant: 6 data centers, measured from the coordinates in the facts above. The table shows the nearest 3.

NameKindSizeStatusDistance
CGI DatacenterData center——17 km
Centerprise International (Distribution)Data center——23 km