Power plant · Blaenau Gwent, Wales, United Kingdom

Rassau Industrial Estate Battery Storage

Rassau Industrial Estate Battery Storage is a battery storage plant under construction in Blaenau Gwent, Wales, United Kingdom, with 6 MW of capacity.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationBlaenau Gwent (coordinates), WalesDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusUnder constructionDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date22 Jan 2020 (permit C/2019/0326, Town and Country Planning Act, issued by Blaenau Gwent)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date25 Nov 2019 (reference C/2019/0326, planning authority Blaenau Gwent)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date22 Jan 2020 (granted, reference C/2019/0326, planning authority Blaenau Gwent)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity6 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBattery (stand-alone storage)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.8038, -3.2307DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its owner.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the owner.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Construction started
  2. Permit granted (planning authority Blaenau Gwent, reference C/2019/0326)
  3. Permit applied for (planning authority Blaenau Gwent, reference C/2019/0326)

How it compares

Rassau Industrial Estate is the 114th-largest of 157 power plants planned, permitted or under construction in Wales and the 2,004th-largest of 2,548 in the United Kingdom by capacity; its 6 MW is <0.1% of the 279,068 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
Wales114th of 15716,088 MW<0.1%
United Kingdom2,004th of 2,548279,068 MW<0.1%
All power plants planned, permitted or under construction in our data5,145th of 5,799657,076 MW<0.1%

Nearby

Within 50 km of this power plant: 6 data centers, measured from the coordinates in the facts above. The table shows the nearest 3.

NameKindSizeStatusDistance
Centerprise International (Distribution)Data center——19 km
Centerprise International NewportData center——31 km
Vantage Data Centers data center, NewportData center——31 km

Place

Other power plants in Wales

All 622 power plants in Wales, United Kingdom

Data on this page