Power plant · Vale of Glamorgan, Wales, United Kingdom

Land At Court Farm

Land At Court Farm is a power plant in Vale of Glamorgan, Wales, United Kingdom, with 2.2 MW of capacity, operated by Sybac Solar International GmbH.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationVale of Glamorgan (coordinates), WalesDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressCourt Farm, Treoes, Bridgend, Mid Glamorgan, CF35 5DDDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2016DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date5 Jun 2015 (permit 2015/00026/FUL, Town and Country Planning Act, issued by Vale of Glamorgan)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date21 Jan 2015 (reference 2015/00026/FUL, planning authority Vale of Glamorgan)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date5 Jun 2015 (granted, reference 2015/00026/FUL, planning authority Vale of Glamorgan)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorSybac Solar International GmbHDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity2.2 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area5.5 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.4984, -3.5149DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Commissioned
  2. Permit granted (planning authority Vale of Glamorgan, reference 2015/00026/FUL)
  3. Permit applied for (planning authority Vale of Glamorgan, reference 2015/00026/FUL)

How it compares

Land At Court Farm is the 367th-largest of 424 power plants in Wales and the 4,109th-largest of 5,050 in the United Kingdom by capacity; its 2.2 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
Wales367th of 4249,068 MW<0.1%
United Kingdom4,109th of 5,050115,622 MW<0.1%
All power plants in our data10,301st of 12,0321,190,447 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Started operating

Nearby

Within 50 km of this power plant: 8 data centers, measured from the coordinates in the facts above. The table shows the nearest 3.

NameKindSizeStatusDistance
CGI DatacenterData center——4.6 km
Centerprise International (Distribution)Data center——25 km
Microsoft Newport data centreData center——33 km

Operator and place

Other power plants in Wales

All 616 power plants in Wales, United Kingdom

Data on this page