Gelligaer 'B' Wind Farm

Gelligaer 'B' Wind Farm is a cancelled power plant in Merthyr Tydfil, Wales, United Kingdom, with 9.8 MW of capacity, operated by South Wales Power and Swalec.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationMerthyr Tydfil (coordinates), WalesDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressGelligaer B Wind Farm Mynydd Fochriw Fochriw Mid GlamorganDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusCancelled (planning application withdrawn)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Onshore or offshoreOnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date26 Jun 2002 (withdrawn, reference T/99/0295, planning authority Merthyr Tydfil)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorSouth Wales Power (South Wales Power / SWALEC)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorSwalec (South Wales Power / SWALEC)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity9.8 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyWind OnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.7235, -3.3018DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Withdrawn (planning authority Merthyr Tydfil, reference T/99/0295)

How it compares

Gelligaer 'B' Wind Farm is the 150th-largest of 424 power plants in Wales and the 1,995th-largest of 5,050 in the United Kingdom by capacity; its 9.8 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
Wales150th of 4249,068 MW0.11%
United Kingdom1,995th of 5,050115,622 MW<0.1%
All power plants in our data7,347th of 12,0321,190,447 MW<0.1%

Nearby

Within 50 km of this power plant: 7 data centers, measured from the coordinates in the facts above. The table shows the nearest 3.

NameKindSizeStatusDistance
Centerprise International (Distribution)Data center——12 km
Centerprise International NewportData center——26 km
Vantage Data Centers data center, NewportData center——26 km

Operators and place

More from South Wales Power

Other power plants in Wales

All 616 power plants in Wales, United Kingdom