Power plant · Dumfries and Galloway, Scotland, United Kingdom

Sunnyside wind cluster

Sunnyside wind cluster is a power plant in Dumfries and Galloway, Scotland, United Kingdom, with 1 MW of capacity, operated by Sunnyside Wind Farm.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationDumfries and Galloway (coordinates), ScotlandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressLand at Sunnyside, Sanquhar, DG4 6JPDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2015DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Onshore or offshoreOnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date19 Dec 2013 (permit 13/P/3/0211, Town and Country Planning Act, issued by Dumfries and Galloway)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date5 Apr 2013 (reference 13/P/3/0211, planning authority Dumfries and Galloway)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date19 Dec 2013 (granted, reference 13/P/3/0211, planning authority Dumfries and Galloway)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorSunnyside Wind FarmDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity1 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Units2 units (0.5 MW per unit)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyWind OnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates55.3803, -3.9463DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Commissioned
  2. Permit granted (planning authority Dumfries and Galloway, reference 13/P/3/0211)
  3. Permit applied for (planning authority Dumfries and Galloway, reference 13/P/3/0211)

How it compares

Sunnyside wind cluster is the 1,281st-largest of 1,326 power plants in Scotland and the 5,508th-largest of 5,723 in the United Kingdom by capacity; its 1 MW is <0.1% of the 136,106 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
Scotland1,281st of 1,32640,645 MW<0.1%
United Kingdom5,508th of 5,723136,106 MW<0.1%
All power plants in our data12,456th of 12,7051,210,931 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Started operating

Nearby

Within 50 km of this power plant: 1 data center, measured from the coordinates in the facts above.

NameKindSizeStatusDistance
Asanti HamiltonData center——46 km

Operator and place

Other power plants in Scotland

All 2093 power plants in Scotland, United Kingdom

Data on this page