New Cumnock Substation is a 33 kV primary substation in Scotland, United Kingdom, with 7.76 MVA of demand headroom, operated by SP Distribution plc (SP Energy Networks, South and Central Scotland licence area).

Map: where New Cumnock lies
55.3777, -4.2166 on OpenStreetMap

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceNEW CUMNOCKSP Energy Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
LocationScotlandSP Energy Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Grid operatorSP Distribution plc (SP Energy Networks, South and Central Scotland licence area)SP Energy Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Demand headroom7.76 MVASP Energy Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Firm capacity10 MVASP Energy Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
LevelPrimary substationSP Energy Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Voltage33 kV (levels 33, 11 kV)SP Energy Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Coordinates55.3777, -4.2166SP Energy Networks open data portal · CC BY 4.0 · checked 25 Oct 2026

Research on this substation and the land around it.Its headroom, connection queue and congestion, who owns the land around it, and an introduction to those owners.

Nearby

Within 50 km of this substation: 362 power plants (80 operating, 3,751 MW), 128 grid connections (69 operating, 839 MW) and 1 data center, measured from the coordinates in the facts above. The table shows the nearest 7, up to 3 per kind.

NameKindSizeStatusDistance
Ashmark Hill Wind FarmPower plant21 MWCancelled1.3 km
Knockshinnoch Wind FarmPower plant4 MWCancelled1.9 km
Pencloe Wind FarmPower plant81 MWUnder construction2.0 km
Harehill Extn Windfarm grid connectionGrid connection29.8 MWOperating6.1 km
Harehill Windfarm grid connectionGrid connection19.6 MWOperating6.1 km
Garlaff Landfill grid connectionGrid connection4.6 MWOperating8.0 km
Asanti HamiltonData center——45 km

Grid operator and place

Grid connections attached to this substation

More from SP Distribution plc

Candidate sites around this substation

6 sites of land near New Cumnock have it as nearest substation. Each site page gives its area, its distance to the substation and its site score; owners are on request.

Other substations in Scotland

All 843 substations in Scotland, United Kingdom

Data on this page