Power plant · Aberdeenshire, Scotland, United Kingdom

Hill of Tillymorgan extension Wind Farm

Hill of Tillymorgan extension Wind Farm is a cancelled wind power plant in Aberdeenshire, Scotland, United Kingdom, with 2.3 MW of capacity.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationAberdeenshire (coordinates), ScotlandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusCancelled (appeal refused)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Onshore or offshoreOnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date26 Jun 2014 (reference APP/2014/2329, planning authority Aberdeenshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date29 Oct 2015 (appeal refused, reference APP/2014/2329, planning authority Aberdeenshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date27 Apr 2015 (refused, reference APP/2014/2329, planning authority Aberdeenshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity2.3 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Units1 units (2.3 MW per unit)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyWind OnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates57.4118, -2.5746DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its owner.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the owner.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit refused (appeal refused, planning authority Aberdeenshire, reference APP/2014/2329)
  2. Permit refused (planning authority Aberdeenshire, reference APP/2014/2329)
  3. Permit applied for (planning authority Aberdeenshire, reference APP/2014/2329)

How it compares

Hill of Tillymorgan extension was cancelled before it was built: it is not ranked among the power plants that run, and its 2.3 MW is not counted in their totals.

Nearby

Within 50 km of this power plant: 145 grid connections (63 operating, 522 MW), 90 substations and 1 data center, measured from the coordinates in the facts above. The table shows the nearest 7, up to 3 per kind.

NameKindSizeStatusDistance
Rothienorman GSPSubstation——3.5 km
Kirkton Farm Wind Turbine Project grid connectionGrid connection6.56 MWOperating4.1 km
Rothie 3 BESS grid connectionGrid connection75 MWPlanned4.6 km
Rothienorman Battery Storage grid connectionGrid connection50 MWPlanned4.6 km
Insch PrimarySubstation——7.6 km
Fyvie PrimarySubstation——11 km
BrightsolidData center——38 km

Place

Other power plants in Scotland

All 2105 power plants in Scotland, United Kingdom