Power plant · Aberdeenshire, Scotland, United Kingdom

Fetteresso Wind Farm (Mid Hill 3)

Fetteresso Wind Farm (Mid Hill 3) is a permitted power plant in Aberdeenshire, Scotland, United Kingdom, with 42 MW of capacity, operated by Fred Olsen Renewables.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationAberdeenshire (coordinates), ScotlandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressFetteresso, StonehavenDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Onshore or offshoreOnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date21 Sept 2022 (permit ECU00001851, Electricity Act 1989 section 36, issued by Scottish Government (S36))DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date3 Jun 2019 (reference ECU00001851, planning authority Scottish Government (S36))DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date21 Sept 2022 (granted, reference ECU00001851, planning authority Scottish Government (S36))DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorFred Olsen RenewablesDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity42 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Units10 unitsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyWind OnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates56.9660, -2.3442DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (planning authority Scottish Government (S36), reference ECU00001851)
  2. Permit applied for (planning authority Scottish Government (S36), reference ECU00001851)

How it compares

Fetteresso Wind Farm (Mid Hill 3) is the 438th-largest of 872 power plants planned, permitted or under construction in Scotland and the 1,323rd-largest of 3,222 in the United Kingdom by capacity; its 42 MW is <0.1% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
Scotland438th of 87299,272 MW<0.1%
United Kingdom1,323rd of 3,222300,461 MW<0.1%
All power plants planned, permitted or under construction in our data2,487th of 6,455664,040 MW<0.1%

Nearby

Within 50 km of this power plant: 100 grid connections (34 operating, 331 MW), 75 substations and 1 data center, measured from the coordinates in the facts above. The table shows the nearest 7, up to 3 per kind.

NameKindSizeStatusDistance
Fetteresso GSPSubstation——0.3 km
Craigneil Wind Farm 42MW grid connectionGrid connection42 MWPlanned2.5 km
The Waters BESS grid connectionGrid connection55 MWPlanned2.7 km
Broadwood grid connectionGrid connection6.56 MWOperating3.9 km
Fiddes GSPSubstation——5.3 km
Stonehaven PrimarySubstation——6.7 km
BrightsolidData center——24 km

Operator and place

More from Fred Olsen Renewables

Other power plants in Scotland

All 2093 power plants in Scotland, United Kingdom

Data on this page