Power plant · Aberdeenshire, Scotland, United Kingdom

Coast Viners Animal Nutrition, Drumlithie - Solar Array & Battery Storage

Coast Viners Animal Nutrition, Drumlithie - Solar Array & Battery Storage is a permitted power plant in Aberdeenshire, Scotland, United Kingdom, with 9.2 MW of capacity, operated by East Coast Viners Renewables Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationAberdeenshire (coordinates), ScotlandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressAdj East Coast Viners Animal Nutrition Drumlithie Stonehaven, AB39 2XQDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date10 Feb 2023 (permit APP/2022/1701, Town and Country Planning Act, issued by Aberdeenshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date18 Aug 2022 (ref. APP/2022/1701, Aberdeenshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date10 Feb 2023 (granted, ref. APP/2022/1701, Aberdeenshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorEast Coast Viners Renewables LimitedDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity9.2 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area22.7 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates56.9200, -2.3330DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Know more about this power plant, or want an introduction to its operator? Ask us.

How it compares

Coast Viners Animal Nutrition, Drumlithie - Solar Array & Battery Storage is the 709th-largest of 872 power plants planned, permitted or under construction in Scotland and the 2,339th-largest of 3,222 in the United Kingdom by capacity; its 9.2 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
Scotland709th of 87299,272 MW<0.1%
United Kingdom2,339th of 3,222300,661 MW<0.1%
All power plants planned, permitted or under construction in our data5,431st of 6,455664,240 MW<0.1%

Nearby

Within 50 km of this power plant: 98 grid connections (29 operating, 303 MW) and 72 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Broadwood grid connectionGrid connection6.56 MWOperating1.3 km
Jacksbank Renewable Energy Park grid connectionGrid connection10 MWPlanned1.3 km
Generation 49.9 MW grid connection at Fettersso GridGrid connection49.9 MWPlanned1.5 km
Fiddes GSPSubstation——1.9 km
Fetteresso GSPSubstation——5.0 km
Stonehaven PrimarySubstation——7.6 km

Operator and place

Other power plants in Scotland

All 2093 power plants in Scotland, United Kingdom

Data on this page