Power plant · East Ayrshire, Scotland, United Kingdom

Ashmark Hill Community Wind Farm

Ashmark Hill Community Wind Farm is a cancelled wind power plant in East Ayrshire, Scotland, United Kingdom, with 21 MW of capacity, operated by Innogy.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEast Ayrshire (coordinates), ScotlandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressLand At Ashmark Hill C90, Afton Road, 5km south of New Cumnock, Mossmark, Strathclyde, KA18 4PRDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusCancelled (planning permission refused)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Onshore or offshoreOnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date1 May 2018 (reference 18/0354/PP, planning authority East Ayrshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date28 Sept 2018 (refused, reference 18/0354/PP, planning authority East Ayrshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorInnogy (applicant)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity21 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Units7 units (3 MW per unit)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyWind OnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates55.3518, -4.2070DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit refused (planning authority East Ayrshire, reference 18/0354/PP)
  2. Permit applied for (planning authority East Ayrshire, reference 18/0354/PP)

How it compares

Ashmark Hill Community Wind Farm is the 478th-largest of 1,342 power plants in Scotland and the 1,428th-largest of 5,837 in the United Kingdom by capacity; its 21 MW is <0.1% of the 200,833 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
Scotland478th of 1,34246,828 MW<0.1%
United Kingdom1,428th of 5,837200,833 MW<0.1%
All power plants in our data4,367th of 13,0281,354,089 MW<0.1%

Nearby

Within 50 km of this power plant: 1 data center, measured from the coordinates in the facts above.

NameKindSizeStatusDistance
Asanti HamiltonData center——48 km

Operator and place

More from Innogy

Other power plants in Scotland

All 2107 power plants in Scotland, United Kingdom

Data on this page