Power plant · Mid Sussex, England, United Kingdom

Worsted Farm

Worsted Farm is a power plant in Mid Sussex, England, United Kingdom, with 5 MW of capacity, operated by S4N Worsted.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationMid Sussex (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressLand At Worsted Farm, Worsted Lane, East Grinstead, West Sussex, RH19 3UFDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2019DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date21 Nov 2016 (permit DM/15/3056, Town and Country Planning Act, issued by Mid Sussex)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date15 Sept 2015 (reference DM/15/3056, planning authority Mid Sussex)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date21 Nov 2016 (appeal granted, reference DM/15/3056, planning authority Mid Sussex)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date21 Nov 2016 (granted, reference DM/15/3056, planning authority Mid Sussex)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date24 Dec 2015 (refused, reference DM/15/3056, planning authority Mid Sussex)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorS4N Worsted (S4N Worsted/)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity5 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area15.1 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.1248, 0.0187DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

How it compares

Worsted Farm is the 1,758th-largest of 3,430 power plants in England and the 2,742nd-largest of 5,050 in the United Kingdom by capacity; its 5 MW is <0.1% of the 115,642 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England1,758th of 3,43071,985 MW<0.1%
United Kingdom2,742nd of 5,050115,642 MW<0.1%
All power plants in our data8,356th of 12,0081,173,302 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Permit issued (Town and Country Planning Act), no. DM/15/3056
  2. Started operating

Nearby

Within 50 km of this power plant: 74 data centers, 35 substations and 16 grid connections (8 operating, 31.3 MW), measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Goldman Sachs data center, East GrinsteadData center——4.4 km
Digital Realty LGW15Data center——14 km
4D Data Centers - GatwickData center——14 km
Five Oaks PrimarySubstation——32 km
Solar 3.905 MW grid connection at Five Oaks Farm PVGrid connection3.91 MWOperating33 km
Billingshurst PrimarySubstation——35 km
Malham Farm Solar & Storage grid connectionGrid connection20 MWPlanned36 km
Plaistow PrimarySubstation——40 km
Solar 4.75 MW grid connection at PlaistowGrid connection4.75 MWOperating41 km