Power plant · Bedford, England, United Kingdom

Twinwood Road Oakley And Clapham, Thurleigh Road - Solar Farm

Twinwood Road Oakley And Clapham, Thurleigh Road - Solar Farm is a permitted power plant in Bedford, England, United Kingdom, with 49.9 MW of capacity, operated by PACE Elevate Energy Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationBedford (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressE/O Twinwood Road Oakley And Clapham, Se/O Thurleigh Road, Milton Ernest And Thurleigh, Bedford, MK41 6BLDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date19 Feb 2026 (permit 25/01292/MAF, Town and Country Planning Act, issued by Bedford)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date4 Jul 2025 (reference 25/01292/MAF, planning authority Bedford)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date19 Feb 2026 (granted, reference 25/01292/MAF, planning authority Bedford)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorPACE Elevate Energy LimitedDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity49.9 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area171 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates52.1852, -0.4876DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (planning authority Bedford, reference 25/01292/MAF)
  2. Permit applied for (planning authority Bedford, reference 25/01292/MAF)

How it compares

Twinwood Road Oakley And Clapham, Thurleigh Road - Solar Farm is the 514th-largest of 2,174 power plants planned, permitted or under construction in England and the 886th-largest of 3,222 in the United Kingdom by capacity; its 49.9 MW is <0.1% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England514th of 2,174185,888 MW<0.1%
United Kingdom886th of 3,222300,461 MW<0.1%
All power plants planned, permitted or under construction in our data1,966th of 6,455664,040 MW<0.1%

Nearby

Within 50 km of this power plant: 17 data centers, 2 grid connections (1 operating, 4.75 MW) and 1 substation, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Pulsant Milton Keynes SE-1Data center——23 km
Data center, England (OSM way 460010263)Data center——23 km
nLighten Milton KeynesData center——28 km
East Claydon GSPSubstation——41 km
Pembridge Farm grid connectionGrid connection131 MWPlanned48 km
Shelswell Solar Park grid connectionGrid connection4.75 MWOperating49 km

Operator and place

Other power plants in England

All 5809 power plants in England, United Kingdom