Power plant · Rugby, England, United Kingdom
Tolldish Hall Farm, Parrotts Grove - Solar Photovoltaic Panels
Tolldish Hall Farm, Parrotts Grove - Solar Photovoltaic Panels is a power plant under construction in Rugby, England, United Kingdom, with 25 MW of capacity, operated by Novus Renewable Services Limited.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Rugby (coordinates), England | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Tolldish Hall Farm Parrotts Grove, Coventry, CV2 1NR | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Under construction | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 31 Aug 2023 (permit 39235, Town and Country Planning Act, issued by Rugby) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 17 Oct 2022 (reference 39235, planning authority Rugby) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 31 Aug 2023 (granted, reference 39235, planning authority Rugby) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Novus Renewable Services Limited | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 25 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Solar Photovoltaics | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Area | 12.7 ha (solar site area) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 52.4589, -1.4498 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.
Request researchHow it compares
Tolldish Hall Farm, Parrotts Grove - Solar Photovoltaic Panels is the 1,108th-largest of 2,174 power plants planned, permitted or under construction in England and the 1,741st-largest of 3,222 in the United Kingdom by capacity; its 25 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 1,108th of 2,174 | 186,088 MW | <0.1% |
| United Kingdom | 1,741st of 3,222 | 300,661 MW | <0.1% |
| All power plants planned, permitted or under construction in our data | 3,376th of 6,455 | 664,240 MW | <0.1% |
Nearby
Within 50 km of this power plant: 7 data centers, measured from the coordinates in the facts above. The table shows the nearest 3.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Data center, England (OSM way 710050084) | Data center | — | — | 10 km |
| Santander data center, England | Data center | — | — | 21 km |
| Santander data center, England | Data center | — | — | 21 km |
Operator and place
More from Novus Renewable Services Limited
- Fairfields Energy Storage System1,025 MW · permitted
- Hall Farm, Hickling Lane - Battery Energy Storage400 MW · planned
- Blackdyke Farm, Blackford - Battery Storage340 MW
- Peterstow Gas Compressor Station, Hentland - Energy Storage System49.9 MW · permitted
- Oaks Farm - Solar Farm37 MW · permitted
- Ducklington Solar Farm36 MW · under construction
- Marsh Lane, Gowhole - Energy Storage System30 MW · permitted
- The Village Of Halse - Solar Array25 MW · permitted
Other power plants in England
- Walpole Flexible Generation Project2,000 MW
- Outer Dowsing Offshore Wind Farm1,500 MW
- Hornsea 2 - Optimus and Breesea1,320 MW
- Hornsea 1 - Heron & Njord1,218 MW
- Atlantic Array One - Bristol Channel Zone1,200 MW
- Five Estuaries - Wind Farm1,080 MW
- Rugeley Power Plant Conversion1,000 MW
- Teesworks Battery Storage Project1,000 MW
Data on this page
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Planning Inspectorate: National Infrastructure Projects. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.