Power plant · West Berkshire, England, United Kingdom

Sulhamstead Solar Field - Stud Farm

Sulhamstead Solar Field - Stud Farm is a permitted power plant in West Berkshire, England, United Kingdom, with 5 MW of capacity, operated by Mulbrick Clean Energy.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationWest Berkshire (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressLand North and S/O Stud Farm, Sulhamstead, Reading, RG7 4EDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (appeal granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date12 Apr 2017 (permit 15/02148/COMIND, Town and Country Planning Act, issued by West Berkshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date18 Aug 2015 (reference 15/02148/COMIND, planning authority West Berkshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date29 Mar 2016 (refused, reference 15/02148/COMIND, planning authority West Berkshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date12 Apr 2017 (appeal granted, reference 15/02148/COMIND, planning authority West Berkshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date12 Apr 2017 (granted, reference 15/02148/COMIND, planning authority West Berkshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorMulbrick Clean EnergyDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity5 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.4078, -1.0589DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (appeal granted, planning authority West Berkshire, reference 15/02148/COMIND)
  2. Permit granted (planning authority West Berkshire, reference 15/02148/COMIND)
  3. Permit refused (planning authority West Berkshire, reference 15/02148/COMIND)
  4. Permit applied for (planning authority West Berkshire, reference 15/02148/COMIND)

How it compares

Sulhamstead Solar Field - Stud Farm is the 1,613th-largest of 2,174 power plants planned, permitted or under construction in England and the 2,484th-largest of 3,222 in the United Kingdom by capacity; its 5 MW is <0.1% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England1,613th of 2,174185,888 MW<0.1%
United Kingdom2,484th of 3,222300,461 MW<0.1%
All power plants planned, permitted or under construction in our data5,616th of 6,455664,040 MW<0.1%

Nearby

Within 50 km of this power plant: 241 substations, 212 grid connections (106 operating, 1,098 MW) and 81 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Trash Green PrimarySubstation——1.0 km
Solar 20.948 MW grid connection at Burghfield ReserveGrid connection20.9 MWPlanned2.5 km
Solar 55.3 MW grid connection at Burghfield ReserveGrid connection55.3 MWPlanned2.5 km
Burghfield grid connectionGrid connection1.6 MWOperating3.0 km
Theale PrimarySubstation——3.1 km
Padworth PrimarySubstation——3.9 km
Pulsant Reading SL3Data center——6.0 km
Redcentric ReadingData center——6.0 km
Asanti - ReadingData center——6.4 km

Operator and place

More from Mulbrick Clean Energy

Other power plants in England

All 5809 power plants in England, United Kingdom