Power plant · Dorset, England, United Kingdom

Southern Counties Shooting Ground Phase 1

Southern Counties Shooting Ground Phase 1 is a power plant in Dorset, England, United Kingdom, with 9 MW of capacity, operated by British Solar Renewables and NextEenrgy Solar Fund.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationDorset (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressLong Ash Lane, Wardon Hill, DT2 9PWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2017DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date8 Sept 2015 (permit WD/D/14/003367, Town and Country Planning Act, issued by Dorset)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date24 Dec 2014 (reference WD/D/14/003367, planning authority Dorset)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date8 Sept 2015 (granted, reference WD/D/14/003367, planning authority Dorset)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorBritish Solar Renewables (British Solar Renewables / NextEenrgy Solar Fund (NESF))DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorNextEenrgy Solar Fund (British Solar Renewables / NextEenrgy Solar Fund (NESF))DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity9 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates50.8215, -2.5531DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Know more about this power plant, or want an introduction to its operator? Ask us.

How it compares

Southern Counties Shooting Ground Phase 1 is the 1,248th-largest of 3,430 power plants in England and the 2,052nd-largest of 5,050 in the United Kingdom by capacity; its 9 MW is <0.1% of the 115,642 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England1,248th of 3,43071,985 MW<0.1%
United Kingdom2,052nd of 5,050115,642 MW<0.1%
All power plants in our data7,421st of 12,0081,173,302 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Permit issued (Town and Country Planning Act), no. WD/D/14/003367
  2. Started operating

Nearby

Within 50 km of this power plant: 198 grid connections (68 operating, 575 MW), 77 substations and 1 data center, measured from the coordinates in the facts above. The table shows the nearest 7, up to 3 per kind.

NameKindSizeStatusDistance
Southern Counties Complex grid connectionGrid connection3.99 MWOperating0.4 km
Cerne Abbas PrimarySubstation——5.2 km
Maiden Newton PrimarySubstation——5.2 km
10MW Cruxton Farm PV grid connectionGrid connection20 MWPlanned6.2 km
Rampisham Down PV grid connectionGrid connection11.4 MWOperating6.4 km
Yetminster PrimarySubstation——7.7 km
Data Vault - Bournemouth BCP01Data center——49 km

Operators and place

More from British Solar Renewables

Other power plants in England

All 5809 power plants in England, United Kingdom