Power plant · King's Lynn and West Norfolk, England, United Kingdom

Sandringham Estate - Solar Array

Sandringham Estate - Solar Array is a permitted power plant in King's Lynn and West Norfolk, England, United Kingdom, with 2.1 MW of capacity, operated by Royal Sandringham Estate.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationKing's Lynn and West Norfolk (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressS/O Admirals Drive, Sandringham, Kings Lynn, PE32 1LNDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date12 Jul 2024 (permit 24/00562/F, Town and Country Planning Act, issued by King's Lynn and West Norfolk)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date9 Apr 2024 (reference 24/00562/F, planning authority King's Lynn and West Norfolk)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date12 Jul 2024 (granted, reference 24/00562/F, planning authority King's Lynn and West Norfolk)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorRoyal Sandringham Estate (applicant)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity2.1 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area2.3 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates52.8340, 0.5237DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (planning authority King's Lynn and West Norfolk, reference 24/00562/F)
  2. Permit applied for (planning authority King's Lynn and West Norfolk, reference 24/00562/F)

How it compares

Sandringham Estate - Solar Array is the 1,425th-largest of 1,651 power plants planned, permitted or under construction in England and the 2,257th-largest of 2,549 in the United Kingdom by capacity; its 2.1 MW is <0.1% of the 279,978 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England1,425th of 1,651172,174 MW<0.1%
United Kingdom2,257th of 2,549279,978 MW<0.1%
All power plants planned, permitted or under construction in our data5,453rd of 5,782643,557 MW<0.1%

Nearby

Within 50 km of this power plant: 3 data centers and 2 transmission lines, measured from the coordinates in the facts above.

NameKindSizeStatusDistance
Kings Lynn B Connection ProjectTransmission line—Permitted16 km
Longmarsh Green EnergyData center—Planned18 km
Positive ParkData center——42 km
Eastern Green Link 3 and Eastern Green Link 4Transmission line—Planned43 km
US Air Force data center, BrandonData center——48 km

Operator and place

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page