Power plant · Newcastle upon Tyne, England, United Kingdom
Responsive Engineering, Scotswood Road - Solar Panels
Responsive Engineering, Scotswood Road - Solar Panels is a permitted power plant in Newcastle upon Tyne, England, United Kingdom, with 1 MW of capacity, operated by Responsive Engineering.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Newcastle upon Tyne (coordinates), England | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Responsive Engineering, Armstrong Works, Scotswood Road, Newcastle Upon Tyne, NE99 1BX | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Permitted (planning permission granted) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 25 Apr 2025 (permit 2025/0303/01/NPV, Town and Country Planning Act, issued by Newcastle upon Tyne) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 6 Mar 2025 (ref. 2025/0303/01/NPV, Newcastle upon Tyne) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 25 Apr 2025 (granted, ref. 2025/0303/01/NPV, Newcastle upon Tyne) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Responsive Engineering | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 1 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Solar Photovoltaics | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 54.9686, -1.6122 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Know more about this power plant, or want an introduction to its operator? Ask us.
How it compares
Responsive Engineering, Scotswood Road - Solar Panels is the 2,080th-largest of 2,174 power plants planned, permitted or under construction in England and the 3,100th-largest of 3,222 in the United Kingdom by capacity; its 1 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 2,080th of 2,174 | 186,088 MW | <0.1% |
| United Kingdom | 3,100th of 3,222 | 300,661 MW | <0.1% |
| All power plants planned, permitted or under construction in our data | 6,333rd of 6,455 | 664,240 MW | <0.1% |
Nearby
Within 50 km of this power plant: 256 grid connections (131 operating, 1,683 MW) and 148 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Close | Substation | — | — | 0.4 km |
| Pilgrim | Substation | — | — | 0.4 km |
| Corporation Street | Substation | — | — | 0.8 km |
| Battery storage 6.555 MW grid connection at Gateshead East | Grid connection | 6.56 MW | Operating | 1.1 km |
| Gas 10.925 MW grid connection at University | Grid connection | 10.9 MW | Operating | 1.5 km |
| Gas 12 MW grid connection at University | Grid connection | 12 MW | Operating | 1.5 km |
Operator and place
Other power plants in England
- Walpole Flexible Generation Project2,000 MW
- Outer Dowsing Offshore Wind Farm1,500 MW
- Hornsea 2 - Optimus and Breesea1,320 MW
- Hornsea 1 - Heron & Njord1,218 MW
- Atlantic Array One - Bristol Channel Zone1,200 MW
- Five Estuaries - Wind Farm1,080 MW
- Rugeley Power Plant Conversion1,000 MW
- Teesworks Battery Storage Project1,000 MW
Data on this page
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- Planning Inspectorate: National Infrastructure Projects. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.