Power plant · Cherwell, England, United Kingdom

Pool Farm, Mill Lane, Stratton - Solar Farm

Pool Farm, Mill Lane, Stratton - Solar Farm is a permitted power plant in Cherwell, England, United Kingdom, with 44 MW of capacity, operated by JBM Solar Projects Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationCherwell (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressPool Farm Mill Lane Stratton Audley, OX27 9BJDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (appeal granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date21 May 2025 (permit 22/03873/F, Town and Country Planning Act, issued by Cherwell)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date3 Jan 2023 (reference 22/03873/F, planning authority Cherwell)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date21 May 2025 (appeal granted, reference 22/03873/F, planning authority Cherwell)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date18 Jul 2024 (refused, reference 22/03873/F, planning authority Cherwell)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date21 May 2025 (granted, reference 22/03873/F, planning authority Cherwell)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorJBM Solar Projects LimitedDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity44 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area67.9 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.9308, -1.1112DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (appeal granted, planning authority Cherwell, reference 22/03873/F)
  2. Permit granted (planning authority Cherwell, reference 22/03873/F)
  3. Permit refused (planning authority Cherwell, reference 22/03873/F)
  4. Permit applied for (planning authority Cherwell, reference 22/03873/F)

How it compares

Pool Farm, Mill Lane, Stratton - Solar Farm is the 818th-largest of 2,174 power plants planned, permitted or under construction in England and the 1,309th-largest of 3,222 in the United Kingdom by capacity; its 44 MW is <0.1% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England818th of 2,174185,888 MW<0.1%
United Kingdom1,309th of 3,222300,461 MW<0.1%
All power plants planned, permitted or under construction in our data2,449th of 6,455664,040 MW<0.1%

Nearby

Within 50 km of this power plant: 91 grid connections (38 operating, 385 MW), 81 substations and 12 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Launton - Battery grid connectionGrid connection40 MWPlanned2.4 km
Bicester North PrimarySubstation——2.9 km
Bicester North BSPSubstation——2.9 km
Part Haveleys Solar Park grid connectionGrid connection45.5 MWPlanned3.3 km
Pembridge Farm grid connectionGrid connection131 MWPlanned3.8 km
Bicester PrimarySubstation——5.1 km
Data center, England (OSM way 1254986167)Data center——21 km
University Shared Data CentreData center——21 km
nLighten Milton KeynesData center——24 km

Operator and place

More from JBM Solar Projects Limited

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page