Power plant · Telford and Wrekin, England, United Kingdom
Myttons Solar Farm
Myttons Solar Farm is a permitted power plant in Telford and Wrekin, England, United Kingdom, with 49.9 MW of capacity, operated by JBM Solar Projects Limited.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Telford and Wrekin (coordinates), England | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Land N/O Roden Lane Farm, TF6 6BP | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Permitted (planning permission granted) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 15 Mar 2021 (permit TWC/2020/0851, Town and Country Planning Act, issued by Telford and Wrekin) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 8 Oct 2020 (reference TWC/2020/0851, planning authority Telford and Wrekin) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 15 Mar 2021 (granted, reference TWC/2020/0851, planning authority Telford and Wrekin) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | JBM Solar Projects Limited | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 49.9 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Solar Photovoltaics | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Area | 123 ha (solar site area) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 52.7507, -2.6506 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.
Request researchLatest events
Dated events about this power plant from official notices and registers, newest first. All recent changes.
- Permit granted (planning authority Telford and Wrekin, reference TWC/2020/0851)
- Permit applied for (planning authority Telford and Wrekin, reference TWC/2020/0851)
How it compares
Myttons Solar Farm is the 514th-largest of 2,174 power plants planned, permitted or under construction in England and the 886th-largest of 3,222 in the United Kingdom by capacity; its 49.9 MW is <0.1% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 514th of 2,174 | 185,888 MW | <0.1% |
| United Kingdom | 886th of 3,222 | 300,461 MW | <0.1% |
| All power plants planned, permitted or under construction in our data | 1,966th of 6,455 | 664,040 MW | <0.1% |
Nearby
Within 50 km of this power plant: 3 transmission lines, 3 data centers and 1 gas storage facility, measured from the coordinates in the facts above.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Reinforcement to North Shropshire Electricity Distribution Network | Transmission line | — | Permitted | 19 km |
| Mid Wales Electricity Connection (N Grid) | Transmission line | — | Cancelled | 32 km |
| Green Gen Vyrnwy Frankton | Transmission line | — | Planned | 36 km |
| Internet Central data center, England | Data center | — | — | 38 km |
| Salinae Hydrogen Storage project | Gas storage facility | — | Planned | 46 km |
| Hutchison 3G | Data center | — | — | 48 km |
| EE Data Centre | Data center | — | — | 49 km |
Operator and place
More from JBM Solar Projects Limited
- Byers Gill Solar Farm180 MW · permitted
- Craig y Perthi Solar Farm99.9 MW
- Ashorne Hill - Solar Farm50 MW · permitted
- Halse Road - Solar Farm & Battery Storage49.9 MW · permitted
- Burthy Row Farm, Trefullock Moor - Solar Farm & Battery Storage49.9 MW · planned
- Chapel Hill - Solar Arrays49.9 MW
- Belvoir Estate - Solar farm49.9 MW · permitted
- Stoneshollow Solar Farm49.9 MW · permitted
Other power plants in England
- Walpole Flexible Generation Project2,000 MW
- Outer Dowsing Offshore Wind Farm1,500 MW
- Hornsea 2 - Optimus and Breesea1,320 MW
- Hornsea 1 - Heron & Njord1,218 MW
- Atlantic Array One - Bristol Channel Zone1,200 MW
- Five Estuaries - Wind Farm1,080 MW
- Rugeley Power Plant Conversion1,000 MW
- Teesworks Battery Storage Project1,000 MW
Data on this page
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Contains public sector information licensed under the Open Government Licence v3.0. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.