Power plant · Bristol, City of, England, United Kingdom
Philip Street Car Breakers
Philip Street Car Breakers is a permitted power plant in Bristol, City of, England, United Kingdom, with 7.2 MW of capacity, operated by Conrad Energy Limited.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Bristol, City of (coordinates), England | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Philip Street Car Breakers, Philip Street, St. Philips Marsh, Bristol, BS2 0TA | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Permitted (planning permission granted) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 29 Jun 2020 (permit 20/01888/F, Town and Country Planning Act, issued by Bristol, City of) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 4 May 2020 (reference 20/01888/F, planning authority Bristol, City of) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 29 Jun 2020 (granted, reference 20/01888/F, planning authority Bristol, City of) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Conrad Energy Limited | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 7.2 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Battery (stand-alone storage) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 51.4485, -2.5656 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.
Request researchLatest events
Dated events about this power plant from official notices and registers, newest first. All recent changes.
- Permit granted (planning authority Bristol, City of, reference 20/01888/F)
- Permit applied for (planning authority Bristol, City of, reference 20/01888/F)
How it compares
Philip Street Car Breakers is the 1,552nd-largest of 2,174 power plants planned, permitted or under construction in England and the 2,399th-largest of 3,222 in the United Kingdom by capacity; its 7.2 MW is <0.1% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 1,552nd of 2,174 | 185,888 MW | <0.1% |
| United Kingdom | 2,399th of 3,222 | 300,461 MW | <0.1% |
| All power plants planned, permitted or under construction in our data | 5,510th of 6,455 | 664,040 MW | <0.1% |
Nearby
Within 50 km of this power plant: 107 grid connections (70 operating, 749 MW), 38 substations, 10 data centers, 2 transmission lines and 1 AI supercomputer, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| University of Bristol Isambard-AI | AI supercomputer | 5,448 H100e | Operating | 8.3 km |
| nLighten Bristol | Data center | — | — | 10 km |
| Hinkley Point C Connection | Transmission line | — | Permitted | 19 km |
| Homewood Farm grid connection | Grid connection | 1 MW | Planned | 21 km |
| Hinkley Point C Connection Project Material Change | Transmission line | — | Planned | 22 km |
| Bradford-On-Avon Primary | Substation | — | — | 24 km |
| Spring Quarry West Primary | Substation | — | — | 24 km |
| Solar 7 MW grid connection at Spring Quarry West | Grid connection | 7 MW | Operating | 24 km |
| Data center, England (OSM way 996865179) | Data center | — | — | 24 km |
Operator and place
More from Conrad Energy Limited
- Burton Green Farm - Battery Energy Storage100 MW · permitted
- Armshead Farm, Armshead Road - Battery Energy Storage Facility50 MW · permitted
- South Leylodge Farmhouse, Kintore - Battery Energy Storage System49.9 MW · permitted
- Landulph Substation, Ellbridge Lane - Battery Energy Storage49.9 MW · permitted
- Larport, Clay Hill Pit - Solar Photovoltaics & Battery storage45 MW
- Torkington Road, Hazel Grove - Solar PV Panels30 MW · planned
- Gypsy Lane, Burnett - Solar PV Arrays24.5 MW
- Clayhill Farm, Greenfield Road - Battery Energy Storage20 MW · permitted
Other power plants in England
- Walpole Flexible Generation Project2,000 MW
- Outer Dowsing Offshore Wind Farm1,500 MW
- Hornsea 2 - Optimus and Breesea1,320 MW
- Hornsea 1 - Heron & Njord1,218 MW
- Atlantic Array One - Bristol Channel Zone1,200 MW
- Five Estuaries - Wind Farm1,080 MW
- Rugeley Power Plant Conversion1,000 MW
- Teesworks Battery Storage Project1,000 MW
Data on this page
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Epoch AI. Epoch AI supercomputers, CC BY 4.0.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Contains public sector information licensed under the Open Government Licence v3.0. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.