Power plant · Somerset, England, United Kingdom

Park Wood Solar Farm

Park Wood Solar Farm is a power plant in Somerset, England, United Kingdom, with 5 MW of capacity, operated by Solar Power Generation Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourcePARK WOOD SOLAR FARMDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
LocationSomerset (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressPark Wood, Butleigh, Glastonbury, BA6DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2011DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date28 Jul 2011 (permit 2011/0781, Town and Country Planning Act, issued by Somerset)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date4 May 2011 (reference 2011/0781, planning authority Somerset)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date28 Jul 2011 (granted, reference 2011/0781, planning authority Somerset)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorSolar Power Generation LimitedDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity5 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area12.8 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.1055, -2.6702DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Know more about this power plant, or want an introduction to its operator? Ask us.

How it compares

Park Wood Solar Farm is the 1,758th-largest of 3,430 power plants in England and the 2,742nd-largest of 5,050 in the United Kingdom by capacity; its 5 MW is <0.1% of the 115,642 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England1,758th of 3,43071,985 MW<0.1%
United Kingdom2,742nd of 5,050115,642 MW<0.1%
All power plants in our data8,356th of 12,0081,173,302 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Started operating
  2. Permit issued (Town and Country Planning Act), no. 2011/0781

Nearby

Within 50 km of this power plant: 324 grid connections (63 operating, 560 MW), 49 substations, 5 data centers and 2 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Street Park Wood PV Farm grid connectionGrid connection——0.4 km
Glastonbury Copley Wood PV Site grid connectionGrid connection——2.6 km
Street Higher Hill PV Farm grid connectionGrid connection——2.6 km
Sparkford PrimarySubstation——12 km
Castle Cary PrimarySubstation——12 km
Chilton Cantello PrimarySubstation——13 km
Tata Communications Highbridge DatacentreData center——25 km
Hinkley Point C ConnectionTransmission line—Permitted26 km
Hinkley Point C Connection Project Material ChangeTransmission line—Planned29 km

Operator and place

More from Solar Power Generation Limited

Other power plants in England

All 5809 power plants in England, United Kingdom