Power plant · Cheshire West and Chester, England, United Kingdom
Native River
Native River is a power plant in Cheshire West and Chester, England, United Kingdom, with 57 MW of capacity, operated by Varco Energy.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Cheshire West and Chester (coordinates), England | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Adj Electricity Substation, CH66 2HD | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Operating (operational) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Start year | 2025 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 16 Apr 2021 (permit 20/04767/FUL, Town and Country Planning Act, issued by Cheshire West and Chester) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 17 Dec 2020 (reference 20/04767/FUL, planning authority Cheshire West and Chester) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 16 Apr 2021 (granted, reference 20/04767/FUL, planning authority Cheshire West and Chester) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Varco Energy | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 57 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Battery (stand-alone storage) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 53.2657, -2.9434 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.
Request researchLatest events
Dated events about this power plant from official notices and registers, newest first. All recent changes.
- Commissioned
- Permit granted (planning authority Cheshire West and Chester, reference 20/04767/FUL)
- Permit applied for (planning authority Cheshire West and Chester, reference 20/04767/FUL)
How it compares
Native River is the 134th-largest of 3,430 power plants in England and the 285th-largest of 5,050 in the United Kingdom by capacity; its 57 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 134th of 3,430 | 71,965 MW | <0.1% |
| United Kingdom | 285th of 5,050 | 115,622 MW | <0.1% |
| All power plants in our data | 1,661st of 12,032 | 1,190,447 MW | <0.1% |
Timeline
Dated facts about this power plant from its sources, oldest first.
- Started operating
Nearby
Within 50 km of this power plant: 119 grid connections (72 operating, 565 MW), 109 substations, 10 data centers, 3 gas storage facilities and 2 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| nLighten Chester | Data center | — | — | 2.5 km |
| nLighten Edge Data Centre Liverpool | Data center | — | — | 8.9 km |
| The Babbage Centre | Data center | — | — | 15 km |
| Bold GSP | Substation | — | — | 25 km |
| Unit 1 Junction Lane grid connection | Grid connection | 5.26 MW | Planned | 29 km |
| Amazon Man 8 grid connection | Grid connection | 1.39 MW | Planned | 30 km |
| Bickerstaffe WTW grid connection | Grid connection | 1.25 MW | Operating | 30 km |
| Newton Le Willows | Substation | — | — | 30 km |
| Haydock | Substation | — | — | 31 km |
Operator and place
Other power plants in England
- Walpole Flexible Generation Project2,000 MW
- Outer Dowsing Offshore Wind Farm1,500 MW
- Hornsea 2 - Optimus and Breesea1,320 MW
- Hornsea 1 - Heron & Njord1,218 MW
- Atlantic Array One - Bristol Channel Zone1,200 MW
- Five Estuaries - Wind Farm1,080 MW
- Rugeley Power Plant Conversion1,000 MW
- Teesworks Battery Storage Project1,000 MW
Data on this page
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- JRC Open Power Plants Database (JRC-PPDB-OPEN), European Commission, Joint Research Centre. JRC Open Power Plants Database (JRC-PPDB-OPEN), CC BY 4.0.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- Dutch power station owners' and operators' pages. Dutch power station owners' and operators' pages, Facts only, each linked to its page.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Contains public sector information licensed under the Open Government Licence v3.0. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.