Power plant · Newark and Sherwood, England, United Kingdom

Land South Off Ollerton Road

Land South Off Ollerton Road is a power plant in Newark and Sherwood, England, United Kingdom, with 4.2 MW of capacity, operated by Anesco.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationNewark and Sherwood (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressLand South Off, Ollerton Road, Edwinstowe, Mansfield, NG21 9QDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2017DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date7 Jun 2016 (permit 15/00875/FULM, Town and Country Planning Act, issued by Newark and Sherwood)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date22 May 2015 (reference 15/00875/FULM, planning authority Newark and Sherwood)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date7 Jun 2016 (appeal granted, reference 15/00875/FULM, planning authority Newark and Sherwood)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date9 Sept 2015 (refused, reference 15/00875/FULM, planning authority Newark and Sherwood)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date7 Jun 2016 (granted, reference 15/00875/FULM, planning authority Newark and Sherwood)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorAnescoDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity4.2 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area10 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates53.1882, -1.0522DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Know more about this power plant, or want an introduction to its operator? Ask us.

How it compares

Land South Off Ollerton Road is the 2,319th-largest of 3,430 power plants in England and the 3,459th-largest of 5,050 in the United Kingdom by capacity; its 4.2 MW is <0.1% of the 115,642 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England2,319th of 3,43071,985 MW<0.1%
United Kingdom3,459th of 5,050115,642 MW<0.1%
All power plants in our data9,193rd of 12,0081,173,302 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Permit issued (Town and Country Planning Act), no. 15/00875/FULM
  2. Started operating

Nearby

Within 50 km of this power plant: 410 grid connections (77 operating, 808 MW), 125 substations, 7 data centers and 3 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Ollerton Solar Farm grid connectionGrid connection——0.7 km
Sherwood Holiday Village grid connectionGrid connection——1.8 km
Eakring Solar Farm, North Laithes Farm, Wellow Road, Eakring, NOTTS, NG22 0AN grid connectionGrid connection——3.8 km
CosthorpeSubstation——21 km
Digital Space DC - NewarkData center——21 km
Kiveton ParkSubstation——21 km
nLighten NottinghamData center——23 km
DinningtonSubstation——24 km
Chesterfield to WillingtonTransmission line—Planned31 km

Operator and place

More from Anesco

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page