Land Parcel North of Goddards is a power plant in Mid Sussex, England, United Kingdom, with 5 MW of capacity, operated by INRG Solar.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Mid Sussex (coordinates), England | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Land Parcel North Of Goddards, Cuckfield Road, Ansty, Haywards Heath, West Sussex, RH17 5AL | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Operating (operational) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Start year | 2016 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 7 Aug 2015 (permit DM/15/1518, Town and Country Planning Act, issued by Mid Sussex) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 7 Apr 2015 (reference DM/15/1518, planning authority Mid Sussex) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 7 Aug 2015 (granted, reference DM/15/1518, planning authority Mid Sussex) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | INRG Solar | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 5 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Solar Photovoltaics | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Area | 11.7 ha (solar site area) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 50.9773, -0.1652 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Know more about this power plant, or want an introduction to its operator? Ask us.
How it compares
Land Parcel North of Goddards is the 1,758th-largest of 3,430 power plants in England and the 2,742nd-largest of 5,050 in the United Kingdom by capacity; its 5 MW is <0.1% of the 115,642 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 1,758th of 3,430 | 71,985 MW | <0.1% |
| United Kingdom | 2,742nd of 5,050 | 115,642 MW | <0.1% |
| All power plants in our data | 8,356th of 12,008 | 1,173,302 MW | <0.1% |
Timeline
Dated facts about this power plant from its sources, oldest first.
- Permit issued (Town and Country Planning Act), no. DM/15/1518
- Started operating
Nearby
Within 50 km of this power plant: 37 grid connections (27 operating, 136 MW), 24 substations and 16 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| IBM Horsham | Data center | — | — | 14 km |
| Digital Realty LGW15 | Data center | — | — | 17 km |
| Digital Realty LGW16 | Data center | — | — | 17 km |
| Five Oaks Primary | Substation | — | — | 20 km |
| Solar 3.905 MW grid connection at Five Oaks Farm PV | Grid connection | 3.91 MW | Operating | 20 km |
| Billingshurst Primary | Substation | — | — | 21 km |
| Malham Farm Solar & Storage grid connection | Grid connection | 20 MW | Planned | 24 km |
| Plaistow Primary | Substation | — | — | 28 km |
| Solar 4.75 MW grid connection at Plaistow | Grid connection | 4.75 MW | Operating | 29 km |
Operator and place
More from INRG Solar
- Little Crow Solar Park150 MW · permitted
- Little Crow Solar Park90 MW · permitted
- Turweston Solar Farm16.7 MW
- Combermere Abbey14 MW
- New Stone House12.5 MW
- Hendre Fawr Farm11.6 MW
- Lower Basset Down Farm10.5 MW
- West Hall Solar Farm7 MW
Other power plants in England
- Walpole Flexible Generation Project2,000 MW
- Outer Dowsing Offshore Wind Farm1,500 MW
- Hornsea 2 - Optimus and Breesea1,320 MW
- Hornsea 1 - Heron & Njord1,218 MW
- Atlantic Array One - Bristol Channel Zone1,200 MW
- Five Estuaries - Wind Farm1,080 MW
- Rugeley Power Plant Conversion1,000 MW
- Teesworks Battery Storage Project1,000 MW
Data on this page
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Planning Inspectorate: National Infrastructure Projects. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.