Power plant · Cherwell, England, United Kingdom

New Stone House

New Stone House is a power plant in Cherwell, England, United Kingdom, with 12.5 MW of capacity, operated by INRG Solar.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationCherwell (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressLand South Of New Stone House, Main Street, Wendlebury, OX25 2PTDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2015DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date17 Jul 2014 (permit 14/00565/F, Town and Country Planning Act, issued by Cherwell)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date10 Apr 2014 (reference 14/00565/F, planning authority Cherwell)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date17 Jul 2014 (granted, reference 14/00565/F, planning authority Cherwell)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorINRG SolarDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity12.5 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area23.9 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.8685, -1.1794DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

How it compares

New Stone House is the 900th-largest of 3,430 power plants in England and the 1,585th-largest of 5,050 in the United Kingdom by capacity; its 12.5 MW is <0.1% of the 115,642 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England900th of 3,43071,985 MW<0.1%
United Kingdom1,585th of 5,050115,642 MW<0.1%
All power plants in our data5,978th of 12,0081,173,302 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Permit issued (Town and Country Planning Act), no. 14/00565/F
  2. Started operating

Nearby

Within 50 km of this power plant: 224 grid connections (53 operating, 537 MW), 108 substations and 17 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
New Stone House Farm PV grid connectionGrid connection8.98 MWOperating0.8 km
Tritax Symmetry Park grid connectionGrid connection8.74 MWPlanned2.3 km
Supernova Solar Farm grid connectionGrid connection16.3 MWOperating2.5 km
Bicester PrimarySubstation——3.3 km
Arncott PrimarySubstation——4.3 km
Bicester North PrimarySubstation——5.5 km
University Shared Data CentreData center——13 km
Data center, England (OSM way 1254986167)Data center——25 km
AWS Didcot Data CentreData center——28 km

Operator and place

Grid connections attached to this power plant

More from INRG Solar

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page