Power plant · East Riding of Yorkshire, England, United Kingdom

Kenley Solar Farm

Kenley Solar Farm is a permitted power plant in East Riding of Yorkshire, England, United Kingdom, with 49.9 MW of capacity, operated by Boom Power Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEast Riding of Yorkshire (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressNorth East And West Of Carr Plantation Ferry Road Wawne, HU7 5XZDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date18 Nov 2022 (permit 22/01208/STPLF, Town and Country Planning Act, issued by East Riding of Yorkshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date18 May 2022 (ref. 22/01208/STPLF, East Riding of Yorkshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date18 Nov 2022 (granted, ref. 22/01208/STPLF, East Riding of Yorkshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorBoom Power LimitedDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity49.9 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area94 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates53.8301, -0.3534DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Know more about this power plant, or want an introduction to its operator? Ask us.

How it compares

Kenley Solar Farm is the 514th-largest of 2,174 power plants planned, permitted or under construction in England and the 886th-largest of 3,222 in the United Kingdom by capacity; its 49.9 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England514th of 2,174186,088 MW<0.1%
United Kingdom886th of 3,222300,661 MW<0.1%
All power plants planned, permitted or under construction in our data1,966th of 6,455664,240 MW<0.1%

Nearby

Within 50 km of this power plant: 274 grid connections (134 operating, 2,247 MW), 127 substations, 1 transmission line and 1 CO2 emitter, measured from the coordinates in the facts above. The table shows the nearest 8, up to 3 per kind.

NameKindSizeStatusDistance
Solar 320 MW grid connection at Creyke Beck Solar DirectGrid connection320 MWPlanned0.3 km
Solar 150 MW grid connection at Kenley House Generation Hub DirectGrid connection150 MWPlanned1.0 km
Solar 30 MW grid connection at Kenley House Generation Hub DirectGrid connection30 MWPlanned1.0 km
Wawne RoadSubstation——3.3 km
Beverley 132/33kVSubstation——4.2 km
Spark Mill LaneSubstation——4.3 km
Continental Link Multi-Purpose InterconnectorTransmission line—Cancelled5.2 km
Aldbrough Hydrogen StorageCO2 emitter—Planned18 km

Operator and place

More from Boom Power Limited

Other power plants in England

All 5809 power plants in England, United Kingdom