Power plant · Newark and Sherwood, England, United Kingdom

Great North Road Solar and Biodiversity Park

Great North Road Solar and Biodiversity Park is a power plant in Newark and Sherwood, England, United Kingdom, with 800 MW of capacity, operated by Elements Green Trent Limited and Elements Green.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationNewark and Sherwood (coordinates), England (East Midlands)Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
LocationNewark and Sherwood (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressLand to the north west of Newark on Trent, west of A1 and north of A617Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
Addressnorth west of Newark on Trent, west of A1 and north of A617, Newark, NG23 6HTDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPlanned (decision)Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPlanned (planning application submitted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date27 Jun 2025 (reference EN010162, planning authority The Planning Inspectorate)Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
Application date27 Jun 2025 (reference EN010162, planning authority The Planning Inspectorate - National Infrastructure)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorElements Green Trent Limited (applicant)Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorElements GreenDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity800 MW (description)Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity800 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBatteryPlanning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsPlanning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area1,758 ha (application boundary)planning.data.gov.uk · record · Open Government Licence v3.0 · checked 24 Oct 2026
Area1,765 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates53.1444, -0.8963Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Also recorded as

2 sources record Great North Road Solar and Biodiversity Park; this page joins their facts, each with its own source. Links to any of the records lead here. How records are matched.

Name in the sourceIdentifierSourceMatched on
Great North Road Solar and Biodiversity Parkasset:pins-nsip:en010162Planning Inspectorate: National Infrastructure Projects—
Great North Road Solar Parkasset:repd:15149DESNZ Renewable Energy Planning Database (REPD)Same similar name, operator and capacity

How it compares

Great North Road Solar and Biodiversity Park is the 47th-largest of 2,174 power plants planned, permitted or under construction in England and the 75th-largest of 3,222 in the United Kingdom by capacity; its 800 MW is 0.27% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England47th of 2,174186,088 MW0.43%
United Kingdom75th of 3,222300,661 MW0.27%
All power plants planned, permitted or under construction in our data134th of 6,455664,240 MW0.12%

Nearby

Within 50 km of this power plant: 100 substations, 99 grid connections (53 operating, 452 MW), 6 data centers and 3 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Digital Space DC - NewarkData center——10 km
Hall Water Treatment Works grid connectionGrid connection1.6 MWOperating16 km
Newton on Trent Water Works grid connectionGrid connection3.1 MWOperating17 km
StowSubstation——24 km
Stow Park Road grid connectionGrid connection1.19 MWOperating24 km
nLighten NottinghamData center——26 km
Lea RoadSubstation——29 km
CosthorpeSubstation——29 km
ExperianData center——34 km

Operators and place

More from Elements Green Trent Limited

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page