Crucis Park is a power plant in Cotswold, England, United Kingdom, with 12.5 MW of capacity, operated by Solar Planning.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Cotswold (coordinates), England | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Crucis Park, Barnsley Road, Ampney Crucis, Cirencester, Gloucestershire, GL7 5DX | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Operating (operational) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Start year | 2014 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 20 Dec 2013 (permit 13/03656/FUL, Town and Country Planning Act, issued by Cotswold) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 22 Aug 2013 (reference 13/03656/FUL, planning authority Cotswold) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 20 Dec 2013 (granted, reference 13/03656/FUL, planning authority Cotswold) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Solar Planning | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 12.5 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Solar Photovoltaics | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Area | 34 ha (solar site area) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 51.7245, -1.9103 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Know more about this power plant, or want an introduction to its operator? Ask us.
How it compares
Crucis Park is the 900th-largest of 3,430 power plants in England and the 1,585th-largest of 5,050 in the United Kingdom by capacity; its 12.5 MW is <0.1% of the 115,642 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 900th of 3,430 | 71,985 MW | <0.1% |
| United Kingdom | 1,585th of 5,050 | 115,642 MW | <0.1% |
| All power plants in our data | 5,978th of 12,008 | 1,173,302 MW | <0.1% |
Timeline
Dated facts about this power plant from its sources, oldest first.
- Permit issued (Town and Country Planning Act), no. 13/03656/FUL
- Started operating
Nearby
Within 50 km of this power plant: 280 grid connections (89 operating, 1,145 MW), 108 substations and 10 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Crucis Park Estate LLP grid connection | Grid connection | 12.6 MW | Planned | 0.3 km |
| Crucis Park PV Farm grid connection | Grid connection | 14.3 MW | Operating | 0.3 km |
| Cirencester PV grid connection | Grid connection | 9.5 MW | Operating | 1.1 km |
| Cirencester Town Primary | Substation | — | — | 4.1 km |
| Whiteway Primary | Substation | — | — | 4.2 km |
| Cirencester BSP | Substation | — | — | 4.4 km |
| Nationwide Swindon Technology Centre | Data center | — | — | 18 km |
| nLighten Swindon | Data center | — | — | 18 km |
| Vodafone | Data center | — | — | 20 km |
Operator and place
Grid connections attached to this power plant
More from Solar Planning
- Defford Aerodrome49.9 MW
- Little Chalfield Solar Farm12 MW
- Land near Manston8.1 MW
- Bumpers Farm Phase 15 MW
- Land South of Shothanger Works3.5 MW
Other power plants in England
- Walpole Flexible Generation Project2,000 MW
- Outer Dowsing Offshore Wind Farm1,500 MW
- Hornsea 2 - Optimus and Breesea1,320 MW
- Hornsea 1 - Heron & Njord1,218 MW
- Atlantic Array One - Bristol Channel Zone1,200 MW
- Five Estuaries - Wind Farm1,080 MW
- Rugeley Power Plant Conversion1,000 MW
- Teesworks Battery Storage Project1,000 MW
Data on this page
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Planning Inspectorate: National Infrastructure Projects. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- Rare Context entity resolution. Rare Context entity resolution, CC0 1.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.