Power plant · Winchester, England, United Kingdom

Concorde Way, Segensworth - Solar Panels

Concorde Way, Segensworth - Solar Panels is a solar power plant under construction in Winchester, England, United Kingdom, with 1.04 MW of capacity.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationWinchester (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusUnder constructionDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date30 Nov 2022 (permit 22/01583/PNSOL, Town and Country Planning Act, issued by Winchester)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date19 Jul 2022 (reference 22/01583/PNSOL, planning authority Winchester)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date30 Nov 2022 (granted, reference 22/01583/PNSOL, planning authority Winchester)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity1.04 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates50.8714, -1.2458DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its owner.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the owner.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Construction started
  2. Permit granted (planning authority Winchester, reference 22/01583/PNSOL)
  3. Permit applied for (planning authority Winchester, reference 22/01583/PNSOL)

How it compares

Concorde Way, Segensworth - Solar Panels is the 1,573rd-largest of 1,650 power plants planned, permitted or under construction in England and the 2,447th-largest of 2,548 in the United Kingdom by capacity; its 1.04 MW is <0.1% of the 279,068 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England1,573rd of 1,650171,264 MW<0.1%
United Kingdom2,447th of 2,548279,068 MW<0.1%
All power plants planned, permitted or under construction in our data5,697th of 5,799657,076 MW<0.1%

Nearby

Within 50 km of this power plant: 235 grid connections (132 operating, 1,162 MW), 182 substations, 8 data centers and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
SCCData center——0.3 km
AstrohouseData center——0.4 km
ServerhouseData center——0.4 km
Whitely PrimarySubstation——0.6 km
Batley's Power Station grid connectionGrid connection19 MWOperating1.3 km
Plessey Titchfield PrimarySubstation——1.4 km
Botley Wood GSPSubstation——1.7 km
Peak GEN Fareham grid connectionGrid connection19 MWOperating1.8 km
99.9MW BESS Titchfield Lane grid connectionGrid connection100 MWPlanned2.6 km

Place

Other power plants in England

All 5872 power plants in England, United Kingdom