Power plant · County Durham, England, United Kingdom
Comeleon House Solar PV Farm
Comeleon House Solar PV Farm is a cancelled power plant in County Durham, England, United Kingdom, with 4 MW of capacity, operated by Durham County Council.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | County Durham (coordinates), England | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Land to South of Comeleon House, Tanfield Lea Industrial Estate, North Stanley, DH9 9NX | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Cancelled (abandoned) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 3 Jun 2015 (permit DM/15/01366/FPA, Town and Country Planning Act, issued by County Durham) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 1 May 2015 (ref. DM/15/01366/FPA, County Durham) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 3 Jun 2015 (granted, ref. DM/15/01366/FPA, County Durham) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Durham County Council | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 4 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Solar Photovoltaics | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Area | 7 ha (solar site area) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 54.8836, -1.7005 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Know more about this power plant, or want an introduction to its operator? Ask us.
How it compares
Comeleon House Solar PV Farm is the 2,350th-largest of 3,430 power plants in England and the 3,494th-largest of 5,050 in the United Kingdom by capacity; its 4 MW is <0.1% of the 115,642 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 2,350th of 3,430 | 71,985 MW | <0.1% |
| United Kingdom | 3,494th of 5,050 | 115,642 MW | <0.1% |
| All power plants in our data | 9,252nd of 12,008 | 1,173,302 MW | <0.1% |
Nearby
Within 50 km of this power plant: 271 grid connections (141 operating, 1,796 MW) and 159 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Tanfield | Substation | — | — | 0.3 km |
| Battery storage and Solar 92.9 MW grid connection at Harperley Lane Direct | Grid connection | 92.9 MW | Planned | 1.8 km |
| Battery storage 49.9 MW grid connection at Coalburn Farm BESS | Grid connection | 49.9 MW | Planned | 3.3 km |
| Solar 3.503 MW grid connection at Annfield 66/20kV | Grid connection | 3.5 MW | Operating | 3.7 km |
| Annfield | Substation | — | — | 4.2 km |
| Annfield 66/20kV | Substation | — | — | 4.2 km |
Operator and place
Other power plants in England
- Walpole Flexible Generation Project2,000 MW
- Outer Dowsing Offshore Wind Farm1,500 MW
- Hornsea 2 - Optimus and Breesea1,320 MW
- Hornsea 1 - Heron & Njord1,218 MW
- Atlantic Array One - Bristol Channel Zone1,200 MW
- Five Estuaries - Wind Farm1,080 MW
- Rugeley Power Plant Conversion1,000 MW
- Teesworks Battery Storage Project1,000 MW
Data on this page
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- Planning Inspectorate: National Infrastructure Projects. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.