Power plant · Cotswold, England, United Kingdom

Cirencester Solar Farm

Cirencester Solar Farm is a power plant in Cotswold, England, United Kingdom, with 10 MW of capacity, operated by Warrington Borough Council and Statkraft.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationCotswold (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressLand Parcel East Of, Wilpit Lane, Preston, Cirencester, GL7 5DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2022DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date17 Sept 2015 (permit 15/01923/FUL, Town and Country Planning Act, issued by Cotswold)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date8 May 2015 (reference 15/01923/FUL, planning authority Cotswold)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date17 Sept 2015 (granted, reference 15/01923/FUL, planning authority Cotswold)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorWarrington Borough Council (Warrington Borough Council / Statkraft)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorStatkraft (Warrington Borough Council / Statkraft)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity10 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBattery (co-located with re)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.7113, -1.9189DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Know more about this power plant, or want an introduction to its operator? Ask us.

How it compares

Cirencester Solar Farm is the 1,102nd-largest of 3,430 power plants in England and the 1,838th-largest of 5,050 in the United Kingdom by capacity; its 10 MW is <0.1% of the 115,642 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England1,102nd of 3,43071,985 MW<0.1%
United Kingdom1,838th of 5,050115,642 MW<0.1%
All power plants in our data7,057th of 12,0081,173,302 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Permit issued (Town and Country Planning Act), no. 15/01923/FUL
  2. Started operating

Nearby

Within 50 km of this power plant: 274 grid connections (89 operating, 1,139 MW), 102 substations and 11 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Cirencester PV grid connectionGrid connection9.5 MWOperating0.5 km
Crucis Park PV Farm grid connectionGrid connection14.3 MWOperating1.5 km
Crucis Park Estate LLP grid connectionGrid connection12.6 MWPlanned1.5 km
Cirencester Town PrimarySubstation——3.0 km
Cirencester BSPSubstation——3.2 km
Whiteway PrimarySubstation——4.0 km
Nationwide Swindon Technology CentreData center——16 km
nLighten SwindonData center——18 km