Power plant · High Peak, England, United Kingdom

Carpenter Plc, Dinting Lodge Industrial Estate - Solar Array

Carpenter Plc, Dinting Lodge Industrial Estate - Solar Array is a permitted solar power plant in High Peak, England, United Kingdom, with 1 MW of capacity, operated by Centrica Business Solutions.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationHigh Peak (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressCarpenter Plc, Dinting Lodge Industrial Estate, Dinting, Glossop, SK13 6LEDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date10 Mar 2025 (permit HPK/2023/0442, Town and Country Planning Act, issued by High Peak)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date31 Oct 2023 (reference HPK/2023/0442, planning authority High Peak)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date10 Mar 2025 (granted, reference HPK/2023/0442, planning authority High Peak)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorCentrica Business Solutions (applicant)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity1 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area2.35 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates53.4512, -1.9752DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (planning authority High Peak, reference HPK/2023/0442)
  2. Permit applied for (planning authority High Peak, reference HPK/2023/0442)

How it compares

Carpenter Plc, Dinting Lodge Industrial Estate - Solar Array is the 1,580th-largest of 1,650 power plants planned, permitted or under construction in England and the 2,457th-largest of 2,548 in the United Kingdom by capacity; its 1 MW is <0.1% of the 279,068 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England1,580th of 1,650171,264 MW<0.1%
United Kingdom2,457th of 2,548279,068 MW<0.1%
All power plants planned, permitted or under construction in our data5,708th of 5,799657,076 MW<0.1%

Nearby

Within 50 km of this power plant: 537 substations, 468 grid connections (260 operating, 2,357 MW), 23 data centers and 3 gas storage facilities, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
HadfieldSubstation——1.1 km
GlossopSubstation——1.1 km
Site 1 (A), Ilkeston Power Limited grid connectionGrid connection6.06 MWOperating1.7 km
SITE 2 grid connectionGrid connection6.06 MWOperating1.7 km
SITE 3 grid connectionGrid connection6.06 MWOperating1.8 km
HattersleySubstation——3.1 km
Data center, England (OSM way 703959498)Data center——13 km
CDL Strata Campus Data CentreData center——14 km
Equinix MA1Data center——17 km

Operator and place

More from Centrica Business Solutions

Other power plants in England

All 5872 power plants in England, United Kingdom