Power plant · Mole Valley, England, United Kingdom

Capel Landfill Site

Capel Landfill Site is a cancelled power plant in Mole Valley, England, United Kingdom, with 1.3 MW of capacity, operated by Sita UK and Surrey Waste Management.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationMole Valley (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressCapel Landfill site , Horsham Road , CapelDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusCancelled (planning application withdrawn)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date31 May 2000 (reference MO 00/0913, planning authority Mole Valley)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date16 Dec 2001 (withdrawn, reference MO 00/0913, planning authority Mole Valley)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorSita UK (Surrey Waste Management / SITA UK)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorSurrey Waste Management (Surrey Waste Management / SITA UK)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity1.3 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyEfW IncinerationDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.1388, -0.3218DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Withdrawn (planning authority Mole Valley, reference MO 00/0913)
  2. Permit applied for (planning authority Mole Valley, reference MO 00/0913)

How it compares

Capel Landfill Site is the 3,166th-largest of 3,430 power plants in England and the 4,704th-largest of 5,050 in the United Kingdom by capacity; its 1.3 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England3,166th of 3,43071,965 MW<0.1%
United Kingdom4,704th of 5,050115,622 MW<0.1%
All power plants in our data11,398th of 12,0321,190,447 MW<0.1%

Nearby

Within 50 km of this power plant: 130 substations, 128 data centers and 86 grid connections (54 operating, 440 MW), measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Digital Realty LGW16Data center——10 km
4D Data Centers - GatwickData center——10 km
Digital Realty LGW15Data center——10 km
Five Oaks PrimarySubstation——12 km
Solar 3.905 MW grid connection at Five Oaks Farm PVGrid connection3.91 MWOperating13 km
Malham Farm Solar & Storage grid connectionGrid connection20 MWPlanned15 km
Billingshurst PrimarySubstation——16 km
Plaistow PrimarySubstation——18 km
Solar 4.75 MW grid connection at PlaistowGrid connection4.75 MWOperating19 km

Operators and place

More from Sita UK

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page