Power plant · North Warwickshire, England, United Kingdom

Camp Farm, Knowle Hill - Solar Farm

Camp Farm, Knowle Hill - Solar Farm is a permitted power plant in North Warwickshire, England, United Kingdom, with 49.9 MW of capacity, operated by Ampyr Solar Europe.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationNorth Warwickshire (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Address400 Metres W/O Camp Farm, Knowle Hill, Hurley, Atherstone, CV9 2JFDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date18 Aug 2025 (permit PAP/2024/0586, Town and Country Planning Act, issued by North Warwickshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date6 Jan 2025 (reference PAP/2024/0586, planning authority North Warwickshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date18 Aug 2025 (granted, reference PAP/2024/0586, planning authority North Warwickshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorAmpyr Solar EuropeDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity49.9 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area75 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates52.5591, -1.6510DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

How it compares

Camp Farm, Knowle Hill - Solar Farm is the 514th-largest of 2,174 power plants planned, permitted or under construction in England and the 886th-largest of 3,222 in the United Kingdom by capacity; its 49.9 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England514th of 2,174186,088 MW<0.1%
United Kingdom886th of 3,222300,661 MW<0.1%
All power plants planned, permitted or under construction in our data1,966th of 6,455664,240 MW<0.1%

Nearby

Within 50 km of this power plant: 7 data centers, measured from the coordinates in the facts above. The table shows the nearest 3.

NameKindSizeStatusDistance
Data center, England (OSM way 710050084)Data center——18 km
EE Data CentreData center——25 km
Hutchison 3GData center——26 km

Operator and place

More from Ampyr Solar Europe

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page