Power plant · Wiltshire, England, United Kingdom

Battens Farm Solar Park

Battens Farm Solar Park is a power plant in Wiltshire, England, United Kingdom, with 11 MW of capacity, operated by Battens Farm Solar Park Ltd.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationWiltshire (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressBattens Farm, Allington, Chippenham, Wiltshire, SN14 6LTDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2014DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date8 Aug 2013 (permit 13/01311/FUL, Town and Country Planning Act, issued by Wiltshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date10 May 2013 (reference 13/01311/FUL, planning authority Wiltshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date8 Aug 2013 (granted, reference 13/01311/FUL, planning authority Wiltshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorBattens Farm Solar Park LtdDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity11 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.4824, -2.1622DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Commissioned
  2. Permit granted (planning authority Wiltshire, reference 13/01311/FUL)
  3. Permit applied for (planning authority Wiltshire, reference 13/01311/FUL)

How it compares

Battens Farm Solar Park is the 1,033rd-largest of 3,430 power plants in England and the 1,758th-largest of 5,050 in the United Kingdom by capacity; its 11 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England1,033rd of 3,43071,965 MW<0.1%
United Kingdom1,758th of 5,050115,622 MW<0.1%
All power plants in our data6,726th of 12,0321,190,447 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Started operating

Nearby

Within 50 km of this power plant: 154 grid connections (97 operating, 1,134 MW), 83 substations, 8 data centers, 2 transmission lines and 1 AI supercomputer, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Battens Farm grid connectionGrid connection10 MWPlanned0.6 km
PV ICP grid connectionGrid connection10.5 MWOperating0.6 km
Yatton Keynell PrimarySubstation——1.5 km
AH Red Barn Solar grid connectionGrid connection40 MWPlanned2.6 km
Rowden PrimarySubstation——3.9 km
Chippenham BSPSubstation——4.1 km
Ark Data CentresData center——8.1 km
Data center, England (OSM way 996865179)Data center——8.2 km
University of Bristol Isambard-AIAI supercomputer5,448 H100eOperating22 km

Operator and place

Grid connections attached to this power plant

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page