Power plant · Gateshead, England, United Kingdom

Albany Road - Solar Array

Albany Road - Solar Array is a permitted power plant in Gateshead, England, United Kingdom, with 2 MW of capacity, operated by Solar Advanced Systems Limited T A Sas Energy.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationGateshead (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressBaltic Business Quarter Albany Road, NE8 3BPDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date10 Dec 2021 (permit DC/21/01206/FUL, Town and Country Planning Act, issued by Gateshead)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date12 Oct 2021 (ref. DC/21/01206/FUL, Gateshead)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date10 Dec 2021 (granted, ref. DC/21/01206/FUL, Gateshead)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorSolar Advanced Systems Limited T A Sas EnergyDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity2 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area3.04 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates54.9669, -1.5882DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Know more about this power plant, or want an introduction to its operator? Ask us.

How it compares

Albany Road - Solar Array is the 1,849th-largest of 2,174 power plants planned, permitted or under construction in England and the 2,806th-largest of 3,222 in the United Kingdom by capacity; its 2 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England1,849th of 2,174186,088 MW<0.1%
United Kingdom2,806th of 3,222300,661 MW<0.1%
All power plants planned, permitted or under construction in our data6,008th of 6,455664,240 MW<0.1%

Nearby

Within 50 km of this power plant: 260 grid connections (134 operating, 1,765 MW) and 153 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Gateshead EastSubstation——0.3 km
Battery storage 6 MW grid connection at Gateshead EastGrid connection6 MWPlanned0.4 km
Battery storage 6.555 MW grid connection at Gateshead EastGrid connection6.56 MWOperating0.5 km
Breamish StreetSubstation——0.8 km
Gateshead CentralSubstation——1.1 km
Newcastle University Agriculture Buildings grid connectionGrid connection3.81 MWPlanned2.4 km