Grid connection · Middlesex County, New Jersey, United States

Sewaren 230 kV grid connection (PJM C01-1493)

Sewaren 230 kV grid connection (PJM C01-1493) is a planned grid connection in Middlesex County, New Jersey, United States, with 18.2 MW of capacity, held by Parkway Generation Operating, LLC.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationMiddlesex County (connects at Sewaren 230 kV)PJM New Services Queue · Free reuse · checked 24 Oct 2026
StatusPlanned (active, cluster C01 Phase 1)PJM New Services Queue · Free reuse · checked 24 Oct 2026
HolderParkway Generation Operating, LLCPJM New Services Queue · Free reuse · checked 24 Oct 2026
Capacity18.2 MWPJM New Services Queue · Free reuse · checked 24 Oct 2026
TechnologyNatural gasPJM New Services Queue · Free reuse · checked 24 Oct 2026
Grid operatorPJM Interconnection, L.L.C.PJM New Services Queue · Free reuse · checked 24 Oct 2026
Queue date27 Apr 2026PJM New Services Queue · Free reuse · checked 24 Oct 2026
Connection date30 Apr 2030 (proposed)PJM New Services Queue · Free reuse · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

Latest events

Dated events about this grid connection from official notices and registers, newest first. All recent changes.

  1. Entered the connection queue

How it compares

Sewaren 230 kV grid connection (PJM C01-1493) is the 69th-largest of 77 grid connections in New Jersey and the 3,771st-largest of 4,021 in the United States by capacity; its 18.2 MW is <0.1% of the 923,876 MW we hold for the United States. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
New Jersey69th of 7711,778 MW0.15%
United States3,771st of 4,021923,876 MW<0.1%
All grid connections in our data5,562nd of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Due to connect

Holder, grid operator and place

More from Parkway Generation Operating, LLC

Other grid connections in New Jersey

All 77 grid connections in New Jersey, United States

Data on this page