Solar 30 MW grid connection at Barnet Grid 33kV

Solar 30 MW grid connection at Barnet Grid 33kV is a planned grid connection in England, United Kingdom, with 30 MW of capacity, held by Deeves Hall Renewables Energy Limited.

Map: where Solar 30 MW grid connection at Barnet Grid 33kV lies
51.6950, -0.2464 on OpenStreetMap

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Barnet Grid 33kV)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
StatusPlanned (accepted to connect)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
HolderDeeves Hall Renewables Energy LimitedUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Capacity30 MWUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
TechnologySolarUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Grid operatorEastern Power Networks plc (UK Power Networks, East England licence area)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Queue date5 Sept 2024UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Voltage33 kVUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Coordinates51.6950, -0.2464UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

How it compares

Solar 30 MW grid connection at Barnet Grid 33kV is the 1,078th-largest of 3,539 grid connections in England and the 1,536th-largest of 4,870 in the United Kingdom by capacity; its 30 MW is <0.1% of the 467,981 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England1,078th of 3,539341,715 MW<0.1%
United Kingdom1,536th of 4,870467,981 MW<0.1%
All grid connections in our data4,855th of 8,6181,355,288 MW<0.1%

Nearby

Within 50 km of this grid connection: 561 substations, 415 power plants (152 operating, 3,166 MW), 139 data centers (1 operating, 88 MW), 1 transmission line and 1 AI supercomputer, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Wrotham Park - Solar PanelsPower plant30 MWPlanned0.6 km
Land At Swanland RoadPower plant5 MWOperating1.9 km
Bell Lane Solar FarmPower plant1 MWCancelled2.9 km
West Potters Bar Primary 11kVSubstation——3.3 km
Shenley Primary 11kVSubstation——3.8 km
Rowley Ln Primary 11kVSubstation——4.4 km
Soverign Data Centre - Metro PointData center——8.2 km
BT Computer CentreData center——9.8 km
Colt London North Data CentreData center——12 km

Holder, grid operator and place

Other grid connections in England

All 4837 grid connections in England, United Kingdom