Grid connection · England, United Kingdom

Oxfo 35MW - PV & Battery grid connection

Oxfo 35MW - PV & Battery grid connection is a planned grid connection in England, United Kingdom, with 35 MW of capacity, held by JBM Solar Projects (UK) Ltd.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceOXFO 35MW - PV & BATTERY grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationEngland (connection site: WITNEY)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (ACCEPTED TO CONNECT)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
HolderJBM Solar Projects (UK) LtdSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toWitney BSP (via: primary)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity35 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologySolarSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyBattery storageSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorSouthern Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date13 Oct 2021SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date31 Aug 2028 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage33 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates51.7771, -1.4383SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its holder? Ask us.

How it compares

Oxfo 35MW - PV & Battery grid connection is the 809th-largest of 2,533 grid connections in England and the 1,254th-largest of 3,903 in the United Kingdom by capacity; its 35 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England809th of 2,533319,370 MW<0.1%
United Kingdom1,254th of 3,903446,745 MW<0.1%
All grid connections in our data4,454th of 7,6161,281,251 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 314 power plants (125 operating, 2,085 MW) and 133 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Tar Solar FarmPower plant40 MWPermitted1.8 km
Tar Solar FarmPower plant49.9 MWPermitted1.8 km
Eynsham Solar FarmPower plant13.2 MWOperating2.2 km
Witney Town PrimarySubstation——3.1 km
Witney BSPSubstation——3.3 km
Eynsham PrimarySubstation——3.7 km

Holder, grid operator and place

Other grid connections in England

All 3831 grid connections in England, United Kingdom

Data on this page