Grid connection · England, United Kingdom

OFF Balderstone RD grid connection

OFF Balderstone RD grid connection is a planned grid connection in England, United Kingdom, with 49.9 MW of capacity, held by Smith Brothers Ltd.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceOFF BALDERSTONE RD grid connectionSP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
LocationEngland (connects at Rochdale SGTS 2 3 4)SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
HolderSmith Brothers LtdSP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity49.9 MWSP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyBattery storageSP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorElectricity North West LimitedSP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date4 Sept 2020SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage132 kVSP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates53.8059, -2.2084SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

How it compares

OFF Balderstone RD grid connection is the 597th-largest of 2,533 grid connections in England and the 904th-largest of 3,903 in the United Kingdom by capacity; its 49.9 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England597th of 2,533319,370 MW<0.1%
United Kingdom904th of 3,903446,745 MW<0.1%
All grid connections in our data4,270th of 7,9281,372,494 MW<0.1%

Nearby

Within 50 km of this grid connection: 506 substations, 328 power plants (106 operating, 743 MW), 17 data centers and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Widow Hill, Balderstone Lane - Battery Energy Storage SystemPower plant70 MWUnder construction0.2 km
BurnleySubstation——0.6 km
Burnley BSPSubstation——0.6 km
Safran Nacelles, Bancroft Road - Solar PanelsPower plant1.04 MWPermitted0.7 km
Queens Park EnergyPower plant1.9 MWOperating0.8 km
HeasandfordSubstation——1.0 km
Lloyds Banking Group CopleyData center——24 km
Data center, England (OSM way 403124345)Data center——24 km
Redcentric Elland Data CentreData center——28 km

Holder, grid operator and place

Other grid connections in England

All 3831 grid connections in England, United Kingdom