Grid connection · England, United Kingdom
Land North East of Newton Road grid connection
Land North East of Newton Road grid connection is a planned grid connection in England, United Kingdom, with 30 MW of capacity, held by Forsa Energy Gas Holdings Limited.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Name in the source | LAND NORTH EAST OF NEWTON ROAD grid connection | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Location | England (connects at Penrith/Shap) | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Status | Planned (accepted to connect) | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Holder | Forsa Energy Gas Holdings Limited | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Attached to | Harker / Hutton GSP (via a grid supply point) | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Capacity | 30 MW | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Technology | Battery storage | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Grid operator | Electricity North West Limited | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Queue date | 3 Apr 2024 | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Voltage | 132 kV | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Coordinates | 54.6677, -2.7762 | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.
Request researchHow it compares
Land North East of Newton Road grid connection is the 857th-largest of 2,533 grid connections in England and the 1,333rd-largest of 3,903 in the United Kingdom by capacity; its 30 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 857th of 2,533 | 319,370 MW | <0.1% |
| United Kingdom | 1,333rd of 3,903 | 446,745 MW | <0.1% |
| All grid connections in our data | 4,846th of 7,928 | 1,372,494 MW | <0.1% |
Nearby
Within 50 km of this grid connection: 120 power plants (36 operating, 278 MW) and 54 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Penrith & Shap BSP | Substation | — | — | 0.2 km |
| Newtongate T11 & T12 | Substation | — | — | 0.2 km |
| Newtongate T13 | Substation | — | — | 0.2 km |
| Grise | Power plant | 27 MW | Cancelled | 0.5 km |
| Omega Proteins - Solar Farm & Battery Storage | Power plant | 2.5 MW | Permitted | 0.8 km |
| Moss Thorn Farm | Power plant | 5.8 MW | Operating | 1.2 km |
Holder, grid operator and place
More from Forsa Energy Gas Holdings Limited
Other grid connections in England
- Bute Hydrogen Project 1 grid connection4,800 MW
- Drax BECCS grid connection3,906 MW
- Drax Power Station grid connection3,906 MW
- Bute Hydrogen Project 2 grid connection3,600 MW
- Bute Hydrogen Project 3 grid connection3,600 MW
- Bute Hydrogen Project 5 grid connection3,600 MW
- Bute Hydrogen Project 6 grid connection3,600 MW
- Hinkley Point C grid connection3,340 MW
Data on this page
- California ISO. CAISO queue report, CAISO Privacy and Terms of Use.
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, Free reuse.
- PJM New Services Queue. PJM New Services Queue, Free reuse.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.