Grid connection · England, United Kingdom

Harefield Solar grid connection

Harefield Solar grid connection is a planned grid connection in England, United Kingdom, with 30 MW of capacity, held by Esmart Networks Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceHAREFIELD SOLAR grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationEngland (connects at Denham Avenue)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
HolderEsmart Networks LimitedSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toDenham Avenue Primary (via a primary substation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity30 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologySolarSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorSouthern Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date24 Oct 2022SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date31 Oct 2038 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage22 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates51.5897, -0.4800SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its holder? Ask us.

How it compares

Harefield Solar grid connection is the 857th-largest of 2,533 grid connections in England and the 1,333rd-largest of 3,903 in the United Kingdom by capacity; its 30 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England857th of 2,533319,370 MW<0.1%
United Kingdom1,333rd of 3,903446,745 MW<0.1%
All grid connections in our data4,564th of 7,6161,281,251 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 361 power plants (113 operating, 979 MW), 169 substations, 155 data centers (1 operating, 88 MW) and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Harefield PrimarySubstation——2.7 km
Denham Avenue PrimarySubstation——2.9 km
Gerrards Cross Sewage Treatment WorksPower plant20 MWPlanned3.5 km
Pinstone Farm, Oxford Road - Battery Energy Storage SystemPower plant60 MWPlanned3.8 km
David Lloyd Leisure, Ducks Hill Road - Solar PanelsPower plant1 MWCancelled3.8 km
Denham BSPSubstation——3.8 km
The Chess BuildingData center——6.9 km
SDC M40 CampusData center—Planned7.9 km
Virtus London7Data center——8.9 km

Holder, grid operator and place

Other grid connections in England

All 3831 grid connections in England, United Kingdom