East Anglia One North grid connection

East Anglia One North grid connection is a planned grid connection in England, United Kingdom, with 880 MW of capacity, held by East Anglia One North Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Friston 400kV Substation)NESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
StatusPlanned (awaiting consents)NESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
HolderEast Anglia One North LimitedNESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
Attached toEast Anglia One NorthNESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
Capacity880 MWNESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
TechnologyWind OffshoreNESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
Grid operatorNational Grid Electricity Transmission plcNESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
Connection date30 Oct 2029 (stage 1, cumulative 860 MW)NESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
Connection date31 Oct 2034 (stage 2, cumulative 880 MW)NESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

How it compares

East Anglia One North grid connection is the 156th-largest of 2,533 grid connections in England and the 221st-largest of 3,903 in the United Kingdom by capacity; its 880 MW is 0.2% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England156th of 2,533319,370 MW0.28%
United Kingdom221st of 3,903446,745 MW0.2%
All grid connections in our data365th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Stage 1 due to connect, 860 MW in total
  2. Stage 2 due to connect, 880 MW in total

Holder, grid operator and place

More from East Anglia One North Limited

Other grid connections in England

All 3831 grid connections in England, United Kingdom

Data on this page