Grid connection · England, United Kingdom
CLD040 Blackpool East grid connection
CLD040 Blackpool East grid connection is a planned grid connection in England, United Kingdom, with 40 MW of capacity, connected by Electricity North West Limited.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Name in the source | CLD040 BLACKPOOL EAST grid connection | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Location | England (connects at Penwortham West GSP / Stanah GSP Group) | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Status | Planned (accepted to connect) | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Capacity | 40 MW | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Technology | Solar | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Technology | Battery storage | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Grid operator | Electricity North West Limited | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Queue date | 16 Dec 2020 | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Voltage | 132 kV | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Coordinates | 53.8189, -2.9770 | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
Know more about this grid connection, or want an introduction to its grid operator? Ask us.
How it compares
CLD040 Blackpool East grid connection is the 740th-largest of 2,533 grid connections in England and the 1,138th-largest of 3,903 in the United Kingdom by capacity; its 40 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 740th of 2,533 | 319,370 MW | <0.1% |
| United Kingdom | 1,138th of 3,903 | 446,745 MW | <0.1% |
| All grid connections in our data | 4,292nd of 7,616 | 1,281,251 MW | <0.1% |
Nearby
Within 50 km of this grid connection: 266 power plants (89 operating, 1,746 MW), 2 transmission lines, 1 gas storage facility and 1 data center, measured from the coordinates in the facts above. The table shows the nearest 7, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Smithy Lane, Staining - Solar PV Panels & BESS | Power plant | 40 MW | Planned | 0.5 km |
| Smithy Lane, Staining - Solar PV Panels & BESS | Power plant | 40 MW | Planned | 0.5 km |
| Land To The South Of Todderstaffe | Power plant | 4.5 MW | Operating | 1.3 km |
| Morgan and Morecambe Offshore Wind Farms Transmission Assets | Transmission line | — | Permitted | 7.5 km |
| Preesall Saltfield Underground Gas Storage | Gas storage facility | — | Cancelled | 9.7 km |
| East Irish Sea Transmission Project | Transmission line | — | Planned | 17 km |
| Data center, England (OSM way 1551100328) | Data center | — | — | 44 km |
Grid operator and place
More from Electricity North West Limited
- The Albion Academy grid connection416 MW
- Heaten Hall Farm BESS grid connection240 MW
- Heaten Hall Farm BESS+Wind grid connection240 MW
- Houghton BESS grid connection240 MW
- Walney 2 Offshore Wind Farm grid connection183 MW
- Bolton Road grid connection179 MW
- WS Lamb 2 grid connection160 MW
- Ormonde Offshore Windfarm grid connection150 MW
Other grid connections in England
- Bute Hydrogen Project 1 grid connection4,800 MW
- Drax BECCS grid connection3,906 MW
- Drax Power Station grid connection3,906 MW
- Bute Hydrogen Project 2 grid connection3,600 MW
- Bute Hydrogen Project 3 grid connection3,600 MW
- Bute Hydrogen Project 5 grid connection3,600 MW
- Bute Hydrogen Project 6 grid connection3,600 MW
- Hinkley Point C grid connection3,340 MW
Data on this page
- California ISO. Checked 2026-10-24. CAISO queue report, CAISO Privacy and Terms of Use.
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, Free reuse.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Planning Inspectorate: National Infrastructure Projects. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- PJM New Services Queue. PJM New Services Queue, Free reuse.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.