Data center · Virginia, United States
CoreWeave Chester VA
CoreWeave Chester VA is a data center in Virginia, United States, with 82 MW of IT power, owned by CoreWeave.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Virginia | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| Address | 1401 Meadowville Technology Parkway, Chester, VA | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| Status | Operating | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| Start year | 2024 | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| Owner | CoreWeave | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| Used by | OpenAI | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| IT power | 82 MW | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| Compute (H100 equivalents) | 88,428 H100e | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| Capital cost | $3.11 bn | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| Chips | H100, B200 | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| Coordinates | 37.3617, -77.3253 | US Census Bureau Geocoder · Public domain · checked 24 Oct 2026 |
Know more about this data center, or want an introduction to its owner? Ask us.
How it compares
CoreWeave Chester VA is the 6th-largest of 7 data centers in Virginia and the 45th-largest of 60 in the United States by IT power; its 82 MW is 0.68% of the 11,978 MW we hold for the United States. Ranks and totals cover the data centers in our data that report their IT power, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| Virginia | 6th of 7 | 1,044 MW | 7.9% |
| United States | 45th of 60 | 11,978 MW | 0.68% |
| All data centers in our data | 53rd of 74 | 14,203 MW | 0.58% |
Nearby
Within 50 km of this data center: 3 power plants (1 operating, 447 MW), measured from the coordinates in the facts above.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Chesterfield | Power plant | 447 MW | Operating | 5.6 km |
| Chester Solar Technology Park, LLC | Power plant | 160 MW | Planned | 13 km |
| Keydet Solar Center | Power plant | 120 MW | Under construction | 17 km |
Owner, user and place
More from CoreWeave
- CoreWeave Denton TX262 MW
- Coreweave Helios132 MW
- CoreWeave Ellendale ND68 MW
- CoreWeave Marble NC65 MW
- CoreWeave Norway42 MW
- CoreWeave Dalton 1 & 228 MW
- CoreWeave Lancaster Greenfield sitedata center · under construction
- CoreWeave Muskogee OKdata center · under construction
Other data centers in Virginia
Data on this page
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Epoch AI. Epoch AI data centers, CC BY 4.0.
- US Census Bureau Geocoder. US Census Bureau Geocoder, Public domain.