Data center · North Dakota, United States
CoreWeave Ellendale ND
CoreWeave Ellendale ND is a data center in North Dakota, United States, with 68 MW of IT power, owned by CoreWeave.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | North Dakota | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| Address | 9685 87th Ave SE, Ellendale, ND 58436 | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| Status | Operating | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| Start year | 2025 | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| Owner | CoreWeave | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| Used by | OpenAI | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| IT power | 68 MW | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| Compute (H100 equivalents) | 93,482 H100e | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| Capital cost | $2.58 bn | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| Chips | B200 | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
| Coordinates | 46.0153, -98.5725 | Epoch AI data centers · CC BY 4.0 · checked 24 Oct 2026 |
Research on this data center and its owner.Who owns it up to the parent company, its power supply, grid connection and planning status, and an introduction to the owner.
Request researchHow it compares
CoreWeave Ellendale ND is the 51st-largest of 60 data centers in the United States by IT power; its 68 MW is 0.57% of the 11,978 MW we hold for the United States. Ranks and totals cover the data centers in our data that report their IT power, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| United States | 51st of 60 | 11,978 MW | 0.57% |
| All data centers in our data | 61st of 75 | 14,257 MW | 0.48% |
Owner, user and place
More from CoreWeave
- CoreWeave Denton TX262 MW
- Coreweave Helios132 MW
- CoreWeave Chester VA82 MW
- CoreWeave Marble NC65 MW
- CoreWeave Norway42 MW
- CoreWeave Dalton 1 & 228 MW
- CoreWeave Lancaster Greenfield sitedata center · under construction
- CoreWeave Muskogee OKdata center · under construction
Data on this page
- Epoch AI. Epoch AI data centers, CC BY 4.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.